Bosnia's 300 MW Gacko plant goes offline due to boiler overheating

Mon 10th July, 2017 9:31am
SARAJEVO, July 10 (Reuters) - Bosnia's 300-megawatt (MW) 
Gacko coal-fired plant  RITE.BJ  went offline on Sunday evening, 
likely due to the overheating of a conduit boiler system, the 
plant's sales and development director said on Monday. 
    "We are working to solve the problem and expect the plant to 
return online tomorrow afternoon," Borivoje Vujicic told Reuters 
by telephone.  
    The Gacko and another 300 MW coal-fired plant at Ugljevik 
are run by Bosnia's second-largest power utility, ERS  ERST.BJ , 
which last week sought to buy power to cover a shortfall in the 
third quarter due to an overhaul at Ugljevik and lower water 
levels.  L8N1JX4P5  
 
 (Reporting by Daria Sito-Sucic; Editing by Louise Heavens) 
 ((daria.sito-sucic@thomsonreuters.com; +38733 295 484; Reuters 
Messaging: daria.sito-sucic.thomsonreuters.com@reuters.net)) 
 
Keywords: BOSNIA RITE GACKO/OUTAGES
© Stockopedia 2021, Refinitiv, Share Data Services.
This site cannot substitute for professional investment advice or independent factual verification. To use it, you must accept our Terms of Use, Privacy and Disclaimer policies.