Sept 21 (Reuters) - Dovre Group Oyj DOV1V.HE :
* REG-TRICON AND SUVIC WILL CONSTRUCT A WASTE-HEAT-TO-ENERGY POWER PLANT FOR FORTUM’S
DISTRICT
HEATING SYSTEM IN KIRKKONUMMI
* POWER PLANT IS PLANNED TO PROVIDE HEAT FROM WINTER 2025-2026 ONWARDS
* WORK WILL COMMENCE IN AUTUMN 2023 AND WILL CONTINUE UNTIL END OF 2025.
* POWER PLANT WILL PROVIDE ENERGY TO FORTUM'S DISTRICT HEATING SYSTEM IN KIRKKONUMMI
* TRICON-SUVIC IS MAIN CONTRACTOR OF PROJECT
* TRICON-SUVIC IS RESPONSIBLE FOR CONSTRUCTION OF BUILDINGS, HEAT-SINK-BATTERY FOUNDATIONS
AND
CONSTRUCTING PUMPING STATION
Source text for Eikon: ID:nGNE3RnyQ2
Further company coverage: DOV1V.HE
(Gdansk Newsroom)
((gdansk.newsroom@thomsonreuters.com; +48 58 7696600;))