Table: French nuclear plant outages and restarts

(Changes start and end dates for multiple outages, adds Cruas 3 under future outages, moves
Paluel 2 to recent restarts)
       April 19 (Reuters) - The following table provides information on outages at French
utility EDF's  EDF.PA  nuclear reactors.
    France has 61,370 megawatts (MW) of nuclear generation capacity provided by 56 reactors,
data from power grid operator RTE shows.
    Reuters estimates 23,200 MW, or about 38% of that capacity is offline. That puts online
availability at 38,170 MW or about 62%.

Please click on the link at the bottom to access the data.
   
 CURRENT OUTAGES                                                                             
                                                                                             
 REACTOR NAME     CAPACITY (MW)     OUTAGE START       EXPECTED RESTART    REASON
                                                                           
 Gravelines 6     900               April 18, 2023     July 17,  2023      Statutory outage
 Nogent 2         1,300             April 15, 2023     Sept. 23, 2023      Statutory outage
 Bugey 4          900               April 15, 2023     April 25, 2023      Planned outage
 Civaux 2         1,500             April 6,  2023     April 21, 2023      Unplanned outage
 Golfech 2        1,300             March 27, 2023     Sept. 4,  2023      Statutory outage
 Cattenom 2       1,300             March 3,  2023     Aug. 12,  2023      Statutory outage
 Dampierre 1      900               Feb. 26,  2023     May 22,   2023      Statutory outage
 Chinon 4         900               Feb. 25,  2023     May 3,    2023      Statutory outage
 St Alban 1       1,300             Feb. 24,  2023     June 28,  2023      Statutory outage
 Paluel 1         1,300             Feb. 18,  2023     May 16,   2023      Statutory outage
 Gravelines 1 +   900               Feb. 11,  2023     June 4,   2023 ND   Statutory outage
 Blayais 4        900               Feb. 11,  2023     May 7,    2023      Statutory outage
 Chinon 1         900               Feb. 7,   2023     Nov. 18,  2023      Statutory outage
 Penly 2          1,300             Aug. 20,  2022     June 11,  2023      Statutory outage
 Blayais 1 +      900               July 31,  2022     May 7,    2023 ND   Statutory outage
 Flamanville 1 +  1,300             April 28, 2022     June 5,   2023 ND   Statutory outage
 Cattenom 3       1,300             March 26, 2022     April 18, 2023      Statutory outage
 Golfech 1 +      1,300             Feb. 26,  2022     June 13,  2023 ND   Statutory outage
 Chooz 1          1,500             Feb. 11,  2022     May 8,    2023      Statutory outage
 Penly 1          1,300             Oct. 2,   2021     May 12,   2023      Statutory outage
                                                                           
 TOTAL OUTAGES    23,200                                                    
                                                                            
 PLANNED OUTAGES                                                                             
 IN FUTURE                                                                 
                                                                           
 Tricastin 2      900               April 21, 2023     July 16,  2023      Statutory outage
 Cruas 4 +        900               May 6,    2023 ND  June 16,  2023 ND   Statutory outage
 Tricastin 4      900               April 29, 2023     June 26,  2023      Statutory outage
 Civaux 1         1,500             May 13,   2023     May  21,  2023      Statutory outage
 Chinon 3         900               May 2,    2023     July 26,  2023      Statutory outage
 Belleville 2     1300              May 3,    2023     Oct. 10,  2023      Statutory outage
 Cruas 1 +        900               May 20,   2023 ND  Aug. 14,  2023 ND   Statutory outage
 Chinon 2         900               May 6,    2023     May 9,    2023      Statutory outage
 Bugey 5          900               May 6,    2023     June 18,  2023      Statutory outage
 Dampierre 4      900               May 27,   2023     July 06,  2023      Statutory outage
 Cattenom 1       1300              May 27,   2023     Nov. 3,   2023      Statutory outage
 Blayais 2        900               May 27,   2023     Nov. 25,  2023      Statutory outage
 Gravelines 2     900               June 10,  2023     Dec. 24,  2023      Statutory outage
 Cattenom 3       1,300             June 10,  2023     July 23,  2023      Statutory outage
 Blayais 3        900               June 24,  2023     Aug. 3,   2023      Statutory outage
 Belleville 1     1,300             June 24,  2023     Dec. 1,   2023      Statutory outage
 Tricastin 3      900               July 15,  2023     Aug. 24,  2023      Statutory outage
 Bugey 2          900               July 22,  2023     Oct. 25,  2023      Statutory outage
 Cruas 3 +        900               Aug. 19,  2023     Sept. 28, 2023      Statutory outage
 Cattenom 3       1,300             Oct. 14,  2023     Nov. 26,  2023      Statutory outage
                                                                           
                                                                           
 RECENT RESTARTS                                                            
                                                                            
 REACTOR NAME     CAPACITY (MW)     OUTAGE START       RESTART DATE        REASON
                                                                           
 Paluel 2 +       1,300             April 18, 2023     April 19, 2023      Unplanned outage
 Paluel 2         1,300             April 8,  2023     April 18, 2023      Planned outage
 Chooz 2          1,500             Feb. 9,   2023     April 15, 2023      Unplanned outage
 Nogent 1         1,300             April 11,  2023    April 13, 2023      Unplanned outage
 Paluel 4         1,300             April 3,  2023     April 4, 2023       Unplanned outage
 Civaux 2         1,500             Nov. 20,  2021     April 3, 2023       Statutory outage
 Bugey 3          900               March 24, 2023     March 29, 2023      Unplanned outage
 Gravelines 2     900               March 11, 2023     March 11, 2023      Planned outage
 Bugey 5          900               Feb. 19,  2023     Feb. 22, 2023       Unplanned outage
 Dampierre 4      900               Feb. 17,  2023     Feb. 22, 2023       Planned outage
 Cruas 4          900               Feb. 18,  2023     Feb. 18, 2023       Planned outage
 Gravelines 4     900               Oct. 26,  2022     Feb. 4,  2023       Statutory outage
 Dampierre 2      900               Feb. 1,   2023     Feb. 2,  2023       Planned outage
 Cattenom 1       1,300             June 11,  2022     Jan. 31  2023       Statutory outage
 Blayais 3        900               Jan. 19,  2023     Jan. 26, 2023       Unplanned outage
 Civaux 1         1,500             Aug. 21,  2021     Jan. 25, 2023       Statutory outage
 Gravelines 3     900               Jan. 16,  2023     Jan. 22, 2023       Unplanned outage
 Tricastin 4      900               Jan. 12,  2023     Jan. 16, 2023       Planned outage
 Chinon 2         900               Jan. 14,  2023     Jan. 15, 2023       Planned outage
 Cruas 2          900               Jan. 14,  2023     Jan. 15, 2023       Planned outage
 
+: Latest change
ND: New date
NOTE: Data excludes partial capacity cuts. Data on those can be seen on RTE's website: https://www.services-rte.com/en/view-data-published-by-rte/downtime-of-generation-resources.html

 (Reporting by Seher Dareen in Bengaluru)