       June 7 (Reuters) - The following table provides information on outages at French
utility EDF's  EDF.PA  nuclear reactors.
    France has 61,370 megawatts (MW) of nuclear generation capacity provided by 56 reactors,
data from power grid operator RTE shows.
    Reuters estimates 26,000 MW, or about 42% of that capacity is offline. That puts online
availability at 35,370 MW or about 58%.

Please click on the link at the bottom to access the data.
   
 CURRENT OUTAGES                                                                             
                                                                                             
 REACTOR NAME     CAPACITY (MW)     OUTAGE START       EXPECTED RESTART    REASON
                                                                           
                                                June               June    
 Paluel 4 +       1,300             2,   2023          7,   2023 ND        Statutory outage
                                                                           
                              900               June               July    
 Cruas 4 +                          3,   2023          14,  2023 ND        Statutory outage
                                                                           
 Dampierre 4      900               May 31,   2023     June 10,  2023      Statutory outage
 Belleville 2     1,300             May 27,   2023     Oct. 6,   2023      Statutory outage
 Cattenom 1       1,300             May 27,   2023     Oct. 9,   2023      Statutory outage
 Tricastin 2      900               May 25,   2023     Aug. 20,  2023      Statutory outage
                              900               May                Aug.    
 Cruas 1 +                          20,   2023         23,  2023 ND        Statutory outage
                                                                           
 Bugey 5          900               May 6,    2023     June 18,  2023      Statutory outage
 Chinon 3         900               May 2,    2023     July 26,  2023      Statutory outage
 Tricastin 4      900               April 22, 2023     June 19,  2023      Statutory outage
 Gravelines 6     900               April 18, 2023     July 17,  2023      Statutory outage
 Nogent 2         1,300             April 15, 2023     Aug. 25,  2023      Statutory outage
 Golfech 2        1,300             March 27, 2023     Sept. 4,  2023      Statutory outage
 Cattenom 2       1,300             March 3,  2023     Aug. 1,   2023      Statutory outage
                              900               Feb.               June    
 Dampierre 1 +                      26,  2023          8,   2023 ND        Statutory outage
                                                                           
 St Alban 1       1,300             Feb. 24,  2023     July 8,   2023      Statutory outage
 Gravelines 1     900               Feb. 11,  2023     July 2,   2023      Statutory outage
                              900               Feb.               June    
 Blayais 4 +                        11,  2023          12,  2023 ND        Statutory outage
                                                                           
 Chinon 1         900               Feb. 7,   2023     Nov. 18,  2023      Statutory outage
 Penly 2          1,300             Aug. 20,  2022     June 11,  2023      Statutory outage
                              900               July               June    
 Blayais 1 +                        31,  2022          17,  2023 ND        Statutory outage
                                                                           
 Flamanville 1    1,300             April 28, 2022     Aug. 13,  2023      Statutory outage
 Golfech 1        1,300             Feb. 26,  2022     June 23,  2023      Statutory outage
 Penly 1          1,300             Oct. 2,   2021     June 11,  2023      Statutory outage
                                                                           
 TOTAL OUTAGES                                                              
                  26,000                                                   
                                                                           
                                                                            
 PLANNED OUTAGES                                                                             
 IN FUTURE                                                                 
                                                                           
 Dampierre 4      900               June 10,  2023     July 20,  2023      Statutory outage
 Gravelines 2     900               June 10,  2023     Dec. 24,  2023      Statutory outage
 Blayais 2        900               June 10,  2023     Dec. 9,   2023      Statutory outage
 Blayais 3        900               June 22,  2023     June 24,  2023      Statutory outage
 Belleville 1     1,300             July 8,   2023     Nov. 30,  2023      Statutory outage
 Tricastin 3      900               July 15,  2023     Aug. 24,  2023      Statutory outage
 Bugey 2          900               July 22,  2023     Oct. 25,  2023      Statutory outage
 Chinon 2         900               Aug. 4,   2023     Aug. 5,   2023      Planned outage
 Cruas 3          900               Aug. 19,  2023     Sept. 28, 2023      Statutory outage
 Nogent 1         1,300             Sept.23,  2023     Feb. 7,   2024      Statutory outage
 Cattenom 3       1,300             Oct. 7,   2023     Nov. 19,  2023      Statutory outage
 Cattenom 4       1,300             Dec. 9,   2023     May 27,   2024      Statutory outage
                                                                           
 RECENT RESTARTS                                                            
                                                                            
 REACTOR NAME     CAPACITY (MW)     OUTAGE START       RESTART DATE        REASON
                                                                           
 Cruas 4          900               May 28,   2023     June 3,   2023      Unplanned outage
 Paluel 1         1,300             Feb. 17,  2023     May 27,   2023      Statutory outage
 Tricastin 1      900               May 25,   2023     May 28,   2023      Unplanned outage
 Cruas 2          900               May 23,   2023     May 24,   2023      Unplanned outage
 Civaux 1         1,500             May 12,   2023     May 19,   2023      Statutory outage
 Dampierre 4      900               May 10,   2023     May 14,   2023      Forced outage
 Chooz 1          1,500             Feb. 11,  2022     May 10,   2023      Statutory outage
 Chinon 4         900               Feb. 25,  2023     May 9,    2023      Statutory outage
 Paluel 2         1,300             April 22, 2023     April 26, 2023      Planned outage
 Bugey 4          900               April 24, 2023     April 27, 2023      Unplanned outage
                                                                           
 
+: Latest change
ND: New date
NOTE: Data excludes partial capacity cuts. Data on those can be seen on RTE's website: https://www.services-rte.com/en/view-data-published-by-rte/downtime-of-generation-resources.html

 (Reporting by Kavya Guduru in Bengaluru)
 ((Kavya.Guduru@thomsonreuters.com;))

Recent news on Electricite de France SA

See all news