By Sabina Zawadzki
LONDON, July 18 (Reuters) - A giant vessel docked at the
port of Moheshkhali in Bangladesh two months ago, propelling the
populous but poor nation into the fast-expanding club of
liquefied natural gas (LNG) buyers.
The Excellence is the latest floating storage and
regasification unit (FSRU), a type of carrier that has
proliferated since 2015 as many countries switch to a cleaner
and increasingly cheaper fuel than oil and coal.
But the young FSRU industry has been beset by more project
delays than successes in the past 12 months as fluctuating
energy prices, shipping rates, government policies and not least
strong demand for gas in China reshape the sector.
With the number of countries importing LNG having risen to
42 from 30 in three years, "plug and play" projects, in which
regasification vessels link to well-worn physical and commercial
infrastructure, are expected to continue if at a slower pace.
But strong Chinese demand for super-chilled LNG has dampened
the allure of projects in other countries by lapping up excess
supply, and new entrants are trying to develop smaller ventures.
"In the last year or so, FSRUs have suffered a bit of a
setback from the stellar growth they were previously enjoying,"
Andrew Buckland, Wood Mackenzie's global LNG trade and shipping
principal analyst, said.
"Some of that is down to conditions unique to particular
proposed projects. But a lot of it is more to do with demand
being stronger than expected in existing conventional markets."
Since a golden period between 2015 and 2017, when almost
half of the world's 34 FSRUs came onstream, projects in Ghana,
Pakistan and Ivory Coast have been scrapped and in countries
such as Chile, Croatia and South Africa, delayed.
Those stung include oil majors such as ExxonMobil XOM.N ,
trading houses including Trafigura and shipping companies that
provide FSRUs such as Norway's Hoegh LNG HLNGH.OL . Some have
backed off; others have regrouped in different configurations.
PLUG AND PLAY
FSRUs are relatively new - the first was put in operation in
2005 by Excelerate, which figured out how to fit an entire LNG
terminal onto a single ship. The unlisted U.S. company, together
with Golar GLNG.O and Hoegh, now dominates the industry.
On the face of it, they have a big advantage over onshore
import terminals - cheaper by half at around $300-400 million,
twice as quick to deliver and flexible to boot because the
vessel can journey to other destinations once it is not needed.
This was shown by Egypt's first FSRU project, completed by
privately owned BW Group within just five months at Ain Sokhna
on the Suez canal.
But the project was an ideal "plug and play" venture:
suffering severe power cuts as its own gas output fell, Egypt
had the infrastructure to accept regasified LNG.
Conversely, Ghana demonstrates the difficulties of what are
still complex projects despite their lower costs and lead times.
The country has yet to enter the LNG club despite coming so
close that two FSRUs were earmarked for two projects.
Here, issues related to the construction of onshore
infrastructure and solid contracts with power plants, the end
consumers of the LNG, delayed and scuppered successive ventures.
The Golar and Hoegh FSRUs were reassigned to other locations.
"Developing countries by their nature have limited capacity
when it comes to policy and regulatory structures," said Lance
Crist, head of natural resources for International Finance Corp,
a World Bank arm that has lent to several FSRU projects.
"Many of these are much smaller markets. You're not talking
about large, liquid markets with established infrastructure
where you can just plug and play," he said.
LESS NEED FOR NEW MARKETS
While the Ghana saga unravelled over the past three years,
global LNG market trends changed the dynamics of FSRU projects.
Rates for transporting LNG rose, boosting the revenues of
LNG shipping companies that were thinking of branching into
FSRUs, and China's demand for gas skyrocketed, soaking up an
anticipated oversupply in the market.
China's environmental drive to convert heating plants from
coal to gas drove 40 percent of global LNG demand growth last
year and increased Chinese gas imports by 15 percent, making it
the second-largest LNG buyer after Japan, the International
Energy Agency said in June.
This created less urgency to open new markets by parking
FSRUs in countries that had hitherto not bought LNG. Existing
terminals, usually underused, took more supplies.
The result has been a slowdown in the delivery of planned
projects.
"Prior to last winter, when it looked like there'd be excess
LNG, creating new demand centres via FSRUs looked a more
attractive strategy than it does now," Buckland said. "Which is
not to say they won't come back to that in the future."
Meanwhile, LNG carrier rates, which slumped to $25,000 per
day in 2017, more than tripled to $85,000 a day. This meant
those companies that operate LNG carriers but wanted to join the
FSRU bonanza had missed the boat - at least for now.
For example, LNG carrier company Flex LNG FLNG.OL backed
out of the FSRU business in May, saying shipping rates and
project delays had made the move unattractive compared to
improved carrier rates, its chief source of revenue.
urn:newsml:reuters.com:*:nL5N1T04RB
LESS IS MORE
Some large projects are still due to come onstream, if at a
slower pace: Ivory Coast is scheduled to become an LNG-buying
nation by 2020 with a Total TOTF.PA project using a Golar
FSRU.
The rush of new projects between 2015 and 2017 together with
predictions of LNG oversupply also attracted trading houses
wanting to secure markets for the rising volumes they bought and
sold.
Trafigura, Vitol and Gunvor have competing plans for FSRUs
in Pakistan after the country became an LNG importer in 2016 but
have failed to get projects in Bangladesh off the ground. Now
the urgency has receded with China's growing appetite for LNG.
L8N1QW6ES urn:newsml:reuters.com:*:nL5N1SM7TW
But there has been a proliferation of much smaller projects:
LNG-to-power ventures, FSRUs for single users such as
gas-intensive fertiliser plants and "petrol stations" for ships
using LNG as bunker fuel in northern Europe.
"The old 'FSRU only' business model is becoming crowded with
pressure on returns," Golar told investors in June, saying it
was turning to LNG-to-power projects to drive some of its
growth.
The World Bank's IFC has also recognised the new trends and
is hunting for more projects.
"We are still in the very early stages of a pretty dramatic
transformation," Crist said. "You require critical mass or
scale. Once you have an anchor project then you can start doing
the milk run - smaller cargos that will proliferate pretty soon
over the next five years."
<^^^^^^^^^^^^^^^^^^^^^^^^^^^^^^^^^^^^^^^^^^^^^^^^^^^^^^^^^^^
Imports of LNG by floating regasification vessels vs select
countries and oil and LNG prices https://reut.rs/2KZZ9j6
^^^^^^^^^^^^^^^^^^^^^^^^^^^^^^^^^^^^^^^^^^^^^^^^^^^^^^^^^^^>
(Reporting by Sabina Zawadzki; Editing by Dale Hudson)
((sabina.zawadzki@thomsonreuters.com; +44 207 542 4051;))