** Shares of Genex Power GNX.AX climb as much as 6.9% to
A$0.155, on track for best session since June 9, if gains hold
** Co achieves energisation for the 50 megawatt/100 megawatt
hour Bouldercombe Battery project in Queensland
** Says energisation signals a major construction milestone
as it enables the project to begin commissioning phase ahead of
full operations commencing
** Adds commissioning phase will be completed over the
coming months
** GNX says upon completion of commissioning, the project
will be operated under the autobidder offtake agreement with
Tesla's TSLA.O Australian unit
** Stock up ~7.4% YTD, as of last close
(Reporting by Upasana Singh in Bengaluru)