TOKYO, Sept 13 (Reuters) - Kyushu Electric Power Co 9508.T
has shut the No.4 reactor at its Genkai nuclear power plant in
southwestern Japan for maintenance, including mandatory upgrades
to protect against attacks and serious accidents, a spokesperson
said on Tuesday.
The utility shut the 1,180 megawatt (MW) reactor on Monday,
with a plan to resume operations in mid-February next year.
Japan adopted stricter security rules after the 2011
Fukushima nuclear power disaster.
The company's No.3 reactor at Genkai is also going through
upgrades and is due to be back online in mid-January.
With the shutdown, Japan has six operating reactors with a
capacity of 5,546 MW.
Many of Japan's reactors are still going through a
relicensing process under safety standards imposed after the
Fukushima disaster.
Nine regional power utilities and a wholesaler, Japan Atomic
Power Co (Japco), now have 33 reactors available for commercial
use, with combined generating capacity of 33,083 MW.
The companies had 54 reactors operating before the Fukushima
disaster.
The table below shows the status of Japan's nuclear power
plants.
The regional utilities are: Chubu Electric Power 9502.T ,
Chugoku Electric Power 9504.T , Hokkaido Electric Power
9509.T , Hokuriku Electric Power 9505.T , Kansai Electric
Power 9503.T , Kyushu Electric Power 9508.T , Shikoku Electric
Power 9507.T , Tohoku Electric Power 9506.T and Tokyo
Electric Power (Tepco) 9501.T .
They are referred to in the table by their regional names.
Company Plant Unit MW Status
Hokkaido Tomari 1 579 Shutdown 22/4/11
Hokkaido Tomari 2 579 Shutdown 26/8/11
Hokkaido Tomari 3 912 Shutdown 5/5/12
Tohoku Onagawa 2 825 Shutdown 6/11/10
Tohoku Onagawa 3 825 Shutdown 11/3/11
Tohoku Higashidori 1 1,100 Shutdown 6/2/11
Tepco Kashiwazaki-Kariwa 1 1,100 Shutdown 6/8/11
Tepco Kashiwazaki-Kariwa 2 1,100 Shutdown 16/7/07
Tepco Kashiwazaki-Kariwa 3 1,100 Shutdown 16/7/07
Tepco Kashiwazaki-Kariwa 4 1,100 Shutdown 16/7/07
Tepco Kashiwazaki-Kariwa 5 1,100 Shutdown 25/1/12
Tepco Kashiwazaki-Kariwa 6 1,356 Shutdown 26/3/12
Tepco Kashiwazaki-Kariwa 7 1,356 Shutdown 23/8/11
Chubu Hamaoka 3 1,100 Shutdown 29/11/10
Chubu Hamaoka 4 1,137 Shutdown 13/5/11
Chubu Hamaoka 5 1,380 Shutdown 14/5/11
Hokuriku Shika 1 540 Shutdown 1/3/11
Hokuriku Shika 2 1,206 Shutdown 11/3/11
Kansai Mihama 3 826 Online 30/8/22
Kansai Takahama 1 826 Shutdown 10/1/11
Kansai Takahama 2 826 Shutdown 25/11/11
Kansai Takahama 3 870 Online 24/7/22
Kansai Takahama 4 870 Shutdown 8/6/22
Kansai Ohi 3 1,180 Shutdown 23/8/22
Kansai Ohi 4 1,180 Online 15/7/22
Chugoku Shimane 2 820 Shutdown 27/1/12
Shikoku Ikata 3 890 Online 6/12/21
Kyushu Genkai 3 1,180 Shutdown 21/1/22
Kyushu Genkai 4 1,180 Shutdown 12/9/22
Kyushu Sendai 1 890 Online 18/12/21
Kyushu Sendai 2 890 Online 11/6/22
Japco Tokai Daini 1 1,100 Shutdown 11/3/11
Japco Tsuruga 2 1,160 Shutdown 7/5/11
Total 33,083
(Reporting by Yuka Obayashi
Editing by David Goodman)