Picture of Iog logo

IOG Iog News Story

0.000.00%
gb flag iconLast trade - 00:00
EnergyHighly SpeculativeMicro Cap

REG - IOG PLC - Corporate and Operational Update

For best results when printing this announcement, please click on link below:
http://newsfile.refinitiv.com/getnewsfile/v1/story?guid=urn:newsml:reuters.com:20230502:nRSB9816Xa&default-theme=true

RNS Number : 9816X  IOG PLC  02 May 2023

2 May 2023

 

IOG plc

 

Corporate and Operational Update

 

IOG plc ("IOG", or "the Company"), (AIM: IOG.L) provides a corporate and
operational update ahead of its Annual General Meeting which is being held at
10.00am this morning. An accompanying presentation is available at the IOG
website and can be accessed via this link: https://bit.ly/3LuKbPW
(https://bit.ly/3LuKbPW)

 

Highlights

·      Blythe H1 producing steadily at 17 mmscf/d gross rate, averaging
14.9 mmscf/d year to date

o  95.4% Operating Efficiency and 86.4% Production Efficiency

·      Steady progress towards resolution of Blythe H2 drilling issues
highlighted on 18 April

o  Targeted onstream by end of Q2, then expected to build up to 30-40 mmscf/d

o  Additional cost impact net to IOG estimated to be £2-3 million

·      Central Cluster: additional conventional gas resources and
several new prospects identified on P2589 licence (32(nd) Round) following
interpretation of reprocessed 3D seismic

·      Southern Cluster: advanced planning for Kelham North/Central
appraisal well

·      Northern Cluster: farm-out process launched for up to 50% of
Goddard with joint venture partner

·      Interviews with regulator on nine 33(rd) Round SNS licence
applications due later this month

o  If successful, these would add valuable discovered resources to each
cluster

·      Cash balance of £31.9m at end of April, of which £6.8m was
restricted

·      Carefully assessing forward capital allocation and evaluating
balance sheet options

 

Rupert Newall, CEO, commented:

 

"While Blythe H1 continues to produce steadily through our co-owned
infrastructure, our team have worked closely with Petrofac and Shelf to handle
the complex well control challenge on H2 safely and professionally. After
coming onstream, H2 production is expected to reach an initial peak 30-40
mmscf/d, enhancing our cash flow. Meanwhile, we continue to carefully manage
costs, optimise the portfolio and evaluate future investment options alongside
our joint venture partner.

 

In that context, we continue to enhance the portfolio via our low-cost
strategy of licensing rounds and 3D seismic reinterpretation. For example, we
have identified valuable further undeveloped discovered conventional gas
resources and exploration upside on our 32(nd) Round P2589 licence, part of
the Central Cluster and within short tie-back distance to the Southwark
platform. Additionally, our nine 33(rd) Round licence applications are also
progressing, potentially adding discovered resources to all four of our
production clusters."

 

Dougie Scott, COO, commented:

 

"The gas/oil kick encountered from the Hauptdolomit has now been controlled
without needing to sidetrack, despite three challenging complications:
significant associated drilling fluid losses, a stuck drill string and a
plugged drillpipe. The 8½" hole section has now been drilled to a revised
depth above the reservoir, where the 7" liner will be run and cemented to
isolate the overpressure. This will enable the well to continue to the
reservoir in the planned 6" hole size."

 

Production: Blythe H1 well

·      The current gross unconstrained H1 production rate is
approximately 17 mmscf/d

·      Over 2023 year to date, average gross production has been 14.9
mmscf/d, factoring in liquid letdowns alongside other Bacton gas streams and
planned H2-related shutdowns

·      Operating Efficiency year to date has been 95.4% and Production
Efficiency 86.4%¹

·      Safe hook-up and commissioning of the H2 well is expected to
require 3-5 days of planned downtime in both May and June respectively

 

Drilling: Blythe H2 well

·      Substantial progress made in resolving the well control challenge
in the Hauptdolomit formation above the reservoir highlighted on 18 April,
limiting the likelihood of needing a sidetrack

·      The situation has been uniquely challenging given the confluence
of abnormal formation pressure with an influx of hydrocarbons, drilling fluid
losses, the bottom-hole assembly becoming stuck and drill string being plugged

·      However, close collaboration between key IOG personnel and the
Petrofac and Shelf Drilling teams has enabled the latter two issues to be
resolved, materially improving the situation

·      Two cement plugs as well as specialist Lost Circulation Materials
have been deployed, significantly mitigating the drilling losses

·      The 8½" hole section has been drilled to a revised depth and 7"
liner will be run and cemented to isolate this section, enabling continuation
of drilling into the reservoir as planned

·      On that basis, the well is targeted onstream by the end of Q2, at
an estimated additional cost impact of £2-3 million net to IOG

o  The initial well cost estimate was £13 million net to IOG, including
associated platform modifications, before any potential tax shelter or
investment allowances

·      In a success case, H2 would deliver several key benefits:

o  Gas production rates initially expected at 30-40 mmscf/d after a ramp-up a
period of displacing liquids in the Saturn Banks Pipeline System

o  Lower aqueous liquid arrivals into Bacton, reducing associated operating
costs

o  Increase in ultimate recovery of Blythe gas reserves

Central Cluster (P1915, P2342, P130, P039, P2589)

·      The Central Cluster entails potential development of at least
five contiguous licences in the broader Vulcan and Jupiter areas of the SNS

·      This includes the Southwark, Nailsworth, Elland and Grafton
fields plus several clearly identified potential additions containing both
conventional and tight gas resources

·      The P2589 Grafton licence, acquired in the 32(nd) UK Offshore
Licensing Round, has undergone 3D seismic reprocessing to Pre-Stack Depth
Migration (PSDM)

·      Interpretation of this data has identified two structures
containing undeveloped conventional gas within the Europa field, which IOG has
renamed Kinnegar

o  Produced by ConocoPhillips over 2000-16, Kinnegar lies approximately 13km
north-east of Southwark and directly south of Grafton

o  These structures initially appear to be of commercial size; further
analysis is underway to establish an estimated contingent resource range

o  Several further exploration targets also identified between Southwark and
Kinnegar

·      The Southwark platform would be the key gathering infrastructure
for the Central Cluster, providing the conduit to the 24" Saturn Banks
Pipeline System into Bacton

·      A technical working group including third-party experts is
progressing a deep-dive assessment of the potential deliverability of the
Southwark A1 and A2 wells, as well as the future Nailsworth and Elland wells

·      If successful, the JV's 33(rd) Round licence applications would
add highly synergistic further discovered gas resources to the Central Cluster

Southern Cluster (P2442)

·      Planning is well advanced for drilling of the Kelham
North/Central appraisal well in continuation from Blythe H2, subject to final
JV approval

·      The appraisal well is intended to prove up a high-return,
fast-payback Southern Cluster potentially including Kelham North, Kelham
Central, Abbeydale, Orrell (which lies partly on block), Thornbridge and
Thornbridge Deep, plus potential 33(rd) Round additions

·      The gross success case appraisal well cost is estimated at
£14-18 million (£7-9 million net to IOG) before any tax shelter or
investment allowance

o  Benefits from attractively priced extension option on the Shelf Drilling
Perseverance rig

·      The current licence term expires on 31 March 2024, following a
six-month extension

Northern Cluster (P2438)

·      The joint venture (JV) of IOG and CalEnergy Resources (UK)
Limited (CER) has initiated a farm-out process to bring in an additional
partner for, in aggregate, an up to 50% working interest of the P2438 Licence
(up to 25% each)

·      Goddard is one of the largest undeveloped SNS gas discoveries
(gross 2C: 115 billion cubic feet), with several potential export routes
including the Saturn Banks infrastructure

·      Advanced planning is underway to drill the Goddard appraisal well
in continuation from Kelham North/Central, at an estimated gross cost of
£14-18 million, before any tax shelter

·      The well would enhance the commerciality of Goddard by confirming
reservoir quality and deliverability, defining the gas-water contact and
obtaining pressure data

·      Goddard is intended to be the core field in a Northern Cluster
potentially including two adjacent Goddard Flank structures and the Southsea
prospect, plus potential 33(rd) Round additions

·      The current licence term expires on 31 March 2024, following a
six-month extension

Corporate

·      The Company held £31.9m in cash at the end of April, of which
£6.8m was restricted

·      Given the current lack of Southwark production, management
continues to carefully control costs, assess all future capital allocation and
evaluate options to optimise the balance sheet

¹ Operating Efficiency factors in unplanned downtime and Production
Efficiency factors in both planned and unplanned downtime.

 

This announcement contains inside information for the purposes of Article 7 of
the Market Abuse Regulation (EU) 596/2014 as it forms part of UK domestic law
by virtue of the European Union (Withdrawal) Act 2018 ("MAR"), and is
disclosed in accordance with the company's obligations under Article 17 of
MAR.

 

Enquiries:

 

 IOG plc                                            +44 (0) 20 7036 1400

 Rupert Newall (CEO)

 Dougie Scott (COO)

 James Chance (Head of Capital Markets & ESG)

 finnCap Ltd                                        +44 (0) 20 7220 0500

 Christopher Raggett / Simon Hicks

 Peel Hunt LLP                                      +44 (0) 20 7418 8900

 Richard Crichton / David McKeown

 Vigo Consulting                                    +44 (0) 20 7390 0230

 Patrick d'Ancona / Finlay Thomson

About IOG:

 

IOG is a UK developer and producer of indigenous offshore gas. The Company
began producing gas in March 2022 via its offshore and onshore Saturn Banks
production infrastructure. In addition to its production assets, IOG operates
several UK Southern North Sea licences containing gas discoveries and
prospects which, subject to future investment decisions, may be commercialised
through the Saturn Banks infrastructure. All its assets are co-owned 50:50
with its joint venture partner CalEnergy Resources (UK) Limited. Further
details of its portfolio can be found at www.iog.co.uk (http://www.iog.co.uk)
.

This information is provided by RNS, the news service of the London Stock Exchange. RNS is approved by the Financial Conduct Authority to act as a Primary Information Provider in the United Kingdom. Terms and conditions relating to the use and distribution of this information may apply. For further information, please contact
rns@lseg.com (mailto:rns@lseg.com)
 or visit
www.rns.com (http://www.rns.com/)
.

RNS may use your IP address to confirm compliance with the terms and conditions, to analyse how you engage with the information contained in this communication, and to share such analysis on an anonymised basis with others as part of our commercial services. For further information about how RNS and the London Stock Exchange use the personal data you provide us, please see our
Privacy Policy (https://www.lseg.com/privacy-and-cookie-policy)
.   END  UPDEAXSFEDPDEFA

Recent news on Iog

See all news