Sept 21 (Reuters) - Magnus Energy Group Ltd MAGN.SI :
* Unit MEG Global Resources Limited and PT Hanjungin have
agreed to terminate participation agreement
* "dam project has been delayed, inter alia, mainly due to
land acquisition issues"
* Contractor has agreed to indemnify group of any losses,
despite early termination as requested by MGR
* Accordingly, contractor shall return S$4 million that has
been invested by group
* Contractor has invested approximately S$1 million in heavy
equipment and working capital
* Early termination of PA - dam project is not expected to
have any material effect on eps of group for fy ending 30 june
2017