April 28 (Reuters) - Mcphy Energy SA MCPHY.PA :
* REG-MCPHY ENERGY: DELAY OF THE CEOG PROJECT AND
POSTPONEMENT OF
THE SUPPLY OF THE ELECTROLYZER
* THIS ORDER INCLUDES DELIVERY OF A HIGH POWER ELECTROLYZER,
16 MW
AUGMENTED MCLYZER
* COMPANY REMAINS A STAKEHOLDER IN THIS PROJECT, PENDING
FURTHER
INFORMATION ON CONTINUATION OF OPERATIONS
* COMPANY IS READY TO TAKE OVER EXECUTION OF PROJECT AS SOON
AS
ITS CLIENT, SIEMENS ENERGY, EXPRESSES ITS INTENTION.
* PENDING FURTHER INFORMATION FROM SIEMENS ENERGY ON
FOLLOW-UP OF
THIS PROJECT, MCPHY HAS TO ASSUME AT THIS STAGE A NEGATIVE
IMPACT ON ITS FIRST HALF REVENUE OF EUR 2 MILLION
* IN THIS CONTEXT, MCPHY ESTIMATES THAT ITS REVENUE FOR
FIRST HALF
OF YEAR WILL BE BETWEEN EUR 6 AND EUR 8 MILLION.
* SPECIFIES THAT IT HAS RECORDED APPROXIMATELY 60% OF CEOG
PROJECT
REVENUE AS OF DECEMBER 31, 2022, WHICH IS NOT AFFECTED BY
SUSPENSION
Source text for Eikon: ID:nGNE8KGCyl
Further company coverage: MCPHY.PA
(Gdansk Newsroom)