Dec 26 (Reuters) - SHS Holdings Ltd SEEH.SI :
* UPDATES ON PROPOSED DESIGN, CONSTRUCTION, OPERATION AND
MAINTENANCE OF A 50MW CAPACITY SOLAR POWER PLANT BY HDFC
SINPOWER
* LIQUIDATED DAMAGES ASSESSED AT US$2,500 PER DAY WILL
ACCRUE FROM
18 APRIL 2018 UNTIL DAY SOLAR POWER PLANT IS COMMISSIONED TO
OPERATE
* MINISTRY OF POWER HAD, ON 19 DEC 2018, GRANTED HDFC AN
EXTENSION
OF PLANNED COMMERCIAL OPERATIONS DATE TO 31 OCT 2019