RNS Number : 5747E Ncondezi Energy Limited 31 October 2022
News Release
Positive Solar Feasibility Draft Delivered
31 October 2022: Ncondezi Energy Limited ("Ncondezi" or the "Company")
(AIM:NCCL) is pleased to provide an update on its 300MW solar photovoltaic
("PV") and Battery Energy Storage System ("BESS") project ("the Solar
Project") Feasibility Study ("FS"):
Highlights
· Final draft of the Solar Project feasibility study for up to
300MW solar PV power plant plus BESS has been delivered by WSP Group Africa
(Pty) Ltd ("WSP")
· FS confirms a technically viable and attractive project,
including:
o Preferred site location selected within Ncondezi Mining Concession area
with no fatal flaws identified
o Phased expansion potential between 30MW to 300MW
o Strong solar resource of 1,980kWh/m(2) (Global Horizontal Irradiation)
o High energy yield of over 2,000kWh/kWp confirms top tier performance
potential
o Inclusion of BESS provides grid ancillary support and ability to optimise
dispatch profile
o Standardised tier 1 solar PV specifications selected reducing capex and
improving performance
o No red flags identified on Environmental and Social Impact Assessment
("ESIA") review
· FS confirms additional specifics that are expected to further
drive a competitive tariff offering, including:
o Updated capex projections falling within the low to medium range for solar
PV projects globally
o Potential for 20% to 30% capex savings through economies of scale
generated by phasing the Solar Project in 100MW phases
o Existing development work enables fast tracking of specific work streams
to Financial Close ("FC") saving costs and time
o Inclusion of BESS provides potential for lower cost concessional financing
· FS indicates phased construction of the Solar Project can deliver
first power up to 60MW within 18 months of achieving FC with the full 300MW
deliverable over 28 months.
· Separate grid connection study completed confirming 2 preferred
grid connection options:
o Options are optimized for the phased expansion of the Solar Project
spreading capex requirements
o Site is situated in close proximity to the cross border interconnectors
making it ideal for regional power trading
o Results to be presented to relevant local authorities for approval
· Updated financial model and tariff proposal targeted during
November 2022
· FS results to be shared with potential off takers to confirm
indicative power demand over the coming months
Working capital update
Further to the announcement made on 30 September 2022, careful cash management
has extended the working capital runway into November 2022. The Company needs,
and intends to secure, additional funding before the end of November 2022 with
various options available and under consideration, including the potential
additional tranche of £150k that may be available, at the discretion of the
lenders, under the terms of the Convertible Loan announced on 16 September
2022.
Ncondezi Chief Executive Officer, Hanno Pengilly said: "I am pleased to report
that the Company's 300MW Solar Project FS has confirmed a technically viable
project with a number of advantages capable of driving a competitive power
tariff whilst maintaining a robust investment return.
The Solar Project is expected to benefit from favourable site conditions which
will help lower costs and maximise energy yields. Transmission studies confirm
multiple feasible connection solutions to strategically connect into the grid
with potential to distribute through the Mozambican northern grid as well as
the wider Southern African region.
The FS was conducted at various plant sizes including 30MW, 60MW, 100MW, 200MW
and 300MW, allowing for optimal plant sizing and phasing analysis,
particularly with respect to identifying economies of scale that can generate
a lower more competitive power tariff. This confirmed the Solar Project
delivered in phases of 100MW would maximise the benefits of economies of
scale, and will form the basis of the first phase of proposed development.
Subsequent phases are expected to improve scale economies and deliver even
more competitive tariffs.
A fast tracked FS programme was achieved through leveraging existing advanced
stage development work from our coal baseload project, and we expect these
benefits to continue as the Solar Project is progressed to Financial Close.
The FS is in final draft form awaiting sign off from Ncondezi which is
expected in the coming weeks. Results of the FS are now being used to update
the project financial model and tariff proposal, with a target completion
during November 2022. This will allow us to update shareholders with more
robust cashflow projections and valuations.
During the same period, we plan to engage relevant local authorities and
potential off takers. It is of critical importance that we now focus on
receiving support for a preferred transmission connection solution as well as
formal offtake interest, and we believe the positive FS with supporting tariff
proposal will strongly position the Company to do so.
Finally, through careful cash management, the Company has been able to extend
its working capital position into November 2022, allowing for further
de-risking of the Solar Project before finalising a funding solution. The
Board is cognisant of the need to secure additional funds in the near future.
Multiple options remain on the table which will be thoroughly explored with
a view to unlocking future value creation while also, as far as possible,
minimising dilution to shareholders.
The Board continues to believe that the strategic review of the Ncondezi Coal
Project and the Company's repositioning as a dedicated renewable energy
developer will make it more attractive to a wider investor audience with
greater access to potential sources of capital.
Further announcements will be made at the appropriate time."
Overview of the Solar Project
The Solar Project will be located within the Ncondezi mining concession 5967C
which covers over 25,000 hectares in the districts of Moatize and Chiuta in
the Tete Province. This is large enough for solar PV generation potential of
over 5,000MW.
It is the intention that the Solar Project will connect to the Mozambique grid
with target power off-takers in Mozambique and the Southern African Power Pool
(SAPP).
The FS Study has taken a modular design approach to the Solar Project
targeting a total 300MW but assessing in increments of 30MW, 60MW, 100MW,
200MW and 300MW.
Solar FS Overview
Site Location
3 preferred site locations with generation potential of c.500MW each were
investigated for their suitability for the Solar Project. All sites confirmed
similar climate conditions and relatively even surfaces, ideal for solar power
generation. No red flags were identified during site visits by WSP during
September 2022.
Following the site visits, a preferred site has been selected based primarily
on its closer proximity to existing grid infrastructure. The site also
benefits from having an existing exclusive land use permit, or DUAT, for the
generation of power.
Solar Resource Assessment
Global Horizontal Irradiance ("GHI") is the biggest indicator of potential
yield of a proposed solar PV plant as it correlates directly with potential
electrical output. The Solar Project is located in the Tete Provence of
Mozambique, an area with solar resources above average for the country. Four
weather datasets were obtained and reviewed for the Solar Project to confirm
the solar energy that can be utilised by the solar modules. To ensure the
solar data used was representative, a minimum of ten years of historical data
was used to reduce any risks relating to inter-annual variation in the solar
resource. Using this information, the FS predicts an average annual GHI of
1,980kWh/m(2) which is considered excellent for the region.
Other meteorological parameters such as ambient temperatures, wind speed and
rainfall were also accessed as part of the solar resource assessment and found
to be of low risk.
Energy Yield Assessment
Solar Project GHI results were used with system design assumptions to estimate
the energy output of the project, achieving a specific yield of over
2,000kWh/kWp and performance ratio over 80%. These results are very positive,
being in line with some of the most competitive grid scale projects in South
Africa. It is worth noting that the specific yield and performance ratio do
not vary considerably as the Solar Project is scaled to 300MW, although the
project will benefit from economies of scale in the overall capex. A summary
of the estimated generation performance is summarised below for each
generation capacity:
Parameter Unit 30 MW 60MW 100 MW 200 MW 300 MW
Specific yield kWh/kWp 2033 2039 2044 2029 2027
Energy Output GWh/year 80 165 286 533 798
Performance Ratio % +80 +80 +80 +80 +80
Grid Connection
A full generation integration study has been completed to determine the
optimal transmission line connection into the Mozambican grid. Various
integration studies have been produced for the coal power project and formed
the basis for the Solar Project assessment.
Working with the relevant local authorities, 6 potential solutions were
investigated taking into account potential scaling of the project, available
or under construction transmission infrastructure and planned generation
plants in the region. Results confirm there is grid capacity for the Solar
Project and more than one feasible evacuation solution. The Solar Project is
also ideally suited to feed power into the Mozambican northern grid as well as
participate in cross border power trading within the Southern African Power
Pool ("SAPP").
Two preferred connection solutions have been identified covering grid
connection distances between 20kms and 40kms. Both options have been optimised
to take into account the phased approach to generation expansions, which also
provides a capex benefit by spreading the cost of connection over the various
phases.
The Company will now seek local authority confirmation of the preferred
transmission solution for the evacuation of power.
Technology Assessment
Based on the energy yield assessment, the FS was able to optimise solar PV
module and invertor equipment selection for the current phase of development.
With the additional benefit of a good site location, standardised tier 1
equipment was able to be selected, allowing the Solar Project to benefit from
the use of mature technologies that are expected to reduce capex and deliver
high quality generation outputs. Further optimisation potential will be
explored at the detailed design stage.
Various BESS technologies were investigated with lithium-ion (Li-ion)
batteries being selected due to their maturity in the market. The Company
already has significant experience with lithium-ion batteries in Mozambique
through delivery of its Commercial & Industrial solar PV plus battery
project in Vilanculos which achieved financial close at the end of 2021. BESS
sizing was explored between 2, 4 and 6 hour discharging batteries, however
final sizing will be finalised based on offtaker requirements.
Economies of Scale
As part of the FS, analysis of project generation sizes between 30 and 300MW
has confirmed that economies of scale begin to be demonstrated from 100MW,
with estimated potential capex savings of 20-30%. These economies of scale are
driven largely by procurement and design efficiencies.
In addition, the transmission line capital requirement between 30MW and 100MW
is broadly flat, reinforcing the advantages of initial generation capacity at
100MW.
Further expansions beyond 100MW will benefit from increased efficiencies
through the ability to leverage off existing established infrastructure at the
project.
The Company plans to utilise the economies of scale to deliver a more
competitive tariff solution than smaller projects being developed in the
region.
CAPEX and OPEX
Please note that capex and opex figures have been provided in ranges so as not
to jeopardise sensitive future negotiations.
Solar PV capital costs were estimated based upon costs associated with recent
projects of a similar nature, market values and from WSP's own knowledge of
the market. These values were then further verified through available market
literature such as IRENA and Lazard.
Based on the information provided in conjunction with WSP's project
experience, a capex range for global solar PV projects was produced:
· Low - $800/kWp
· Mid - $1200/kWp
· High- $2000/kWp
The Solar Project capex requirements are expected to fall within the low to
medium range due to its site location, equipment selection and, for sizing
above 100MW, economies of scale.
As with capex estimation, values have been estimated based on costs associated
with recent projects of a similar nature and the IRENA and Lazard Study
Reports. A tolerance has been added to reflect the range of prices that may be
offered by an O&M Contractor:
Opex per kWp per year has been estimated as follows:
· Low Range Estimate - $9.50 / kWp/yr
· Mid-Range Estimate - $13.00 / kWp/yr
· High Range Estimate - $19.00 / kWp/yr
The Solar Project is expected to fall within the low to medium range due to
the reasons outlined above.
Transmission capex is quoted separately and will be provided in more detail
following receipt of transmission solution approval.
Pricing of the BESS was based on several assumptions including benchmarking
prices against quotes from tier 1 suppliers. The final BESS capital costs will
be refined once sizing requirements from off takers is better understood.
Capex and opex assumptions are to be further refined once offtaker
requirements are better understood and detailed engineering and design studies
are finalised. Using this information, the figures will be updated based on
quotes from Engineering Procurement and Construction ("EPC") companies
following the launch of an EPC tender process, although the Company may go out
to tender for indicative bids earlier than this.
ESIA Red Flag Review
WSP conducted a red flag review of the Company's existing ESIA and supporting
documentation completed on the Company's coal power project and mine, with no
major issues identified. As the Solar Project is planned to be installed
within the coal project's concession area, the existing ESIA, which was
approved by the Mozambican authorities, can be utilised and updated to meet
the latest requirements, local and international standards. This is expected
to save significant cost and time for the Solar Project in preparing the ESIA
for approval.
Next Steps
The FS results provide key inputs to update the Solar Project tariff financial
model. This is crucial to establish a more robust valuation for the project at
the various generation stages as well as provide a tariff proposal for offtake
negotiations. Given the positive draft FS results, the Company is targeting
the delivery of an attractive project with a competitive tariff offering. The
Company expects to have this work completed during November 2022 and will
update shareholders as appropriate.
In the same time period, the FS results will also be presented to the relevant
Mozambican authorities to receive additional support to progress to the next
phase, including confirmation of preferred grid connection solution and
project design parameters. Potential off takers are also to be engaged in
parallel to confirm potential power demand.
The Company also expects to approach a select group of Engineering Procurement
and Construction ("EPC") companies for indicative equipment pricing to further
strengthen the capex and opex forecasts in the tariff model.
Enquiries
For further information please visit www.ncondezienergy.com or contact:
Ncondezi Energy Hanno Pengilly +27 (0) 71 362 3566
Scott Mathieson, Edward Thomas, Kane Collings +44 (0) 20 3100 2000
Liberum Capital Limited
NOMAD & Joint Broker
Novum Securities Limited Colin Rowbury +44 (0) 20 7399 9427
Joint Broker
Elizabeth Johnson +44 (0) 777 56 55 927
Pimlico Advisory Ltd
Investor Relations
This announcement contains inside information for the purposes of Article 7 of
Regulation (EU) No 596/2014 which is part of UK law by virtue of
the European Union (Withdrawal) Act 2018. Upon publication of this
Announcement and such information is now considered to be in the public
domain. The person who arranged for the release of this announcement on behalf
of the Company was Hanno Pengilly.
About Ncondezi Energy
Ncondezi is an African power development company focused on the development of
renewable and baseload energy solutions at its concession located in the Tete
Province, northern Mozambique.
The Company is focused on providing reliable and affordable energy to
Mozambique to meet growing energy demands. Our projects support Mozambique's
energy strategy of universal electricity access by 2030. According to the
World Bank, only 30% of the Mozambican population had access to energy in
2017. Our projects would provide reliable and available power helping to close
the infrastructure gap of the region and serving as a catalyst for economic
development.
This information is provided by RNS, the news service of the London Stock Exchange. RNS is approved by the Financial Conduct Authority to act as a Primary Information Provider in the United Kingdom. Terms and conditions relating to the use and distribution of this information may apply. For further information, please contact
rns@lseg.com (mailto:rns@lseg.com)
or visit
www.rns.com (http://www.rns.com/)
.
RNS may use your IP address to confirm compliance with the terms and conditions, to analyse how you engage with the information contained in this communication, and to share such analysis on an anonymised basis with others as part of our commercial services. For further information about how RNS and the London Stock Exchange use the personal data you provide us, please see our
Privacy Policy (https://www.lseg.com/privacy-and-cookie-policy)
. END MSCURVKRUUUROAA