April 20 (Reuters) - 29Metals Ltd 29M.AX :
* PROVIDES AN UPDATE REGARDING IMPACT OF MARCH 2023 EXTREME
WEATHER EVENT
* RECOVERY PLANNING FOR SAFE RETURN TO MINING AND MINERAL
PROCESSING OPERATIONS AT CAPRICORN COPPER IS NEARING COMPLETION
* FOR CAPRICON COPPER, RECOVERY WILL COMPRISE PHASE 1 (MID
SEP-QUARTER 2023) AND PHASE 2 (MID-H1 2024)
* IN THIS RECOVERY PLANNING PERIOD, 29METALS IS CLOSELY
MONITORING
AND MANAGING COST FOR CAPRICORN COPPER
* WILL ALSO CONTINUE TO INVESTIGATE OPPORTUNITIES TO
ACCELERATE
PHASE 2 OF THE RECOVERY FOR CAPRICORN COPPER
* EXPECTS TO FINALISE ITS RECOVERY PLAN BY MID-MAY FOR
CAPRICORN
COPPER
Source text for Eikon: ID:nASX672Pgp