Dec 21 (Reuters) - 3U HOLDING AG :
* Announced on Sunday withdrawal from sale of wind farm
project
* It had been determined on both sides that some conditions
were not met, and so the contract was cancelled
* Parties had stated that there is no consensus alternative
to rescind the contract
* Commissioning in spring 2016
* Sales and earnings impact in 2015 is more than offset by
future sales and profits
* 3U ENERGY PE GmbH will push ahead the construction of the
wind farm, so that the initial operation is still scheduled for
the second quarter 2016
* Essential target figures will barely reach the lower limit
of the prognosis to date
* Now sees FY 2015 sales 47 million euros ($51 million)- 50
million euros ($54 million) ($51 million - $54 million);
previous prognosis: 50 million - 53 million euros
* Now sees FY earnings: -1.3 million euros to -0.9 million
euros; previous prognosis: -1.0 million and 1.0 million euros
* In the fourth quarter 2015 the first positive quarterly
earnings at the Group level of the last four years is expected,
despite lack of the one-off effect of sale proceeds
Source text for Eikon: urn:newsml:reuters.com:*:nPex7CXFjN
Further company coverage: [UUUG.DE ]
($1 = 0.9199 euros)
(Gdynia Newsroom)