April 27 (Reuters) - Adbri Ltd ABC.AX :
* ADBRI LTD - KWINANA UPGRADE PROJECT UPDATE
* ADBRI LTD - REMAINING CAPITAL COMMITMENT FOR PROJECT
COMPLETION
IS NOW ESTIMATED TO BE BETWEEN APPROXIMATELY A$185 MILLION -
A$220 MILLION FOR KWINANA
* ADBRI LTD - AS AT END OF MARCH 2023, ADBRI HAD COMMITTED
A$199
MILLION FOR KWINANA PROJECT, WITH A$143 MILLION SPENT
* ADBRI LTD SEES TOTAL PROJECT COST ESTIMATE FOR KWINANA
UPGRADE
TO BETWEEN A$385 MILLION - A$420 MILLION
* ADBRI - STRUCTURAL & PIPING QUANTITIES AT KWINANA GREATER
THAN
ANTICIPATED, FURTHER IMPACTING ON PROCUREMENT AND CONSTRUCTION
COSTS AND HOURS
* ADBRI - REVIEW CONFIRMED PROJECT REMAINS ON TRACK FOR
TARGET
COMMISSIONING IN Q2 2024, WITH NEW PLANT EXPECTED TO BE FULLY
OPERATIONAL IN Q3 2024
Source text for Eikon: ID:nASXqf9LQ