Anglo-Eastern Plant - Indonesia New Mill Operation Update

For best results when printing this announcement, please click on link below:
http://newsfile.refinitiv.com/getnewsfile/v1/story?guid=urn:newsml:reuters.com:20230509:nRSI8303Ya&default-theme=true

RNS Number : 8303Y  Anglo-Eastern Plantations PLC  09 May 2023

9 May
2023

 

Anglo-Eastern Plantations Plc

("AEP", "Group" or "Company")

 

 
 Indonesia New Mill Operation Update

 

Anglo-Eastern Plantations Plc ("AEP"), a major producer of palm oil and to a
lesser extent rubber with plantations across Indonesia and Malaysia, today
announces an unfortunate incident at the HPP mill causing the tragic loss of
lives of four employees of the contractor. Accordingly, there is likely to be
a delay in the commercial operation of the seventh mill in Indonesia.

 

As AEP mentioned in its 2022 Annual Report, published on 21 April 2023, the
HPP mill was earmarked for completion by the first half of 2023.

 

AEP regrets to announce an unfortunate incident which occurred on 6 May 2023,
resulted in the tragic loss of lives. The four employees of the contractor
died in an explosion while they were working on the Anaerobic Tank Digester at
the HPP mill. The incident occurred whilst the contractor was conducting final
trials and tests before handing over the project on completion.

 

AEP conveys its profound sadness and condolences to the families of those who
lost their lives in the incident and will endeavour to support the families
following the tragic events.

 

The affected area is now cordoned off by the police who will conduct an
investigation into the cause of the explosion.

 

The HPP plantation's operation in the production of FFB is unaffected by this
incident, despite the delay to the operational date for the newly built mill.
It is expected that the delay in completion will be approximately six months.

 

The contracting company who employed the four affected employees is assessing
the damages and extent of repair works. AEP understands that the contracting
company is insured for such losses and expects there to be no financial impact
to AEP.

 

For further enquiry, contact:-

 

Anglo-Eastern Plantations Plc

Dato' John Lim Ewe Chuan                        +44 (0)
20 7216 4621

 

Panmure Gordon (UK) Limited

Dominic
Morley
+44 (0) 20 7886 2954

This information is provided by RNS, the news service of the London Stock Exchange. RNS is approved by the Financial Conduct Authority to act as a Primary Information Provider in the United Kingdom. Terms and conditions relating to the use and distribution of this information may apply. For further information, please contact
rns@lseg.com (mailto:rns@lseg.com)
 or visit
www.rns.com (http://www.rns.com/)
.

RNS may use your IP address to confirm compliance with the terms and conditions, to analyse how you engage with the information contained in this communication, and to share such analysis on an anonymised basis with others as part of our commercial services. For further information about how RNS and the London Stock Exchange use the personal data you provide us, please see our
Privacy Policy (https://www.lseg.com/privacy-and-cookie-policy)
.   END  UPDFLFFVEEIAIIV

Recent news on AEP Plantations

See all news