April 9 (Reuters) - AFRIKA GOLD AG GOG1.H :
* OPERATOR OF LANCASTER GOLD MINE PUSHED AHEAD WITH FURTHER
NECESSARY UPGRADES OF THE PLANT AND HAS BEEN ABLE TO STABILIZE
PRODUCTION IN RECENT WEEKS DESPITE NEW DIFFICULTIES
* LOCAL PROBLEMS SUCH AS REPEATED THEFT OF POWER CABLES OR
DIFFICULTIES IN THE OVERALL PROCESS ARE CONTINUOUSLY ADDRESSED
* PAYMENTS FOR THE OPERATION OF THE FACILITY BY THE OPERATOR
HAVE
BEEN RECEIVED AND WILL BE USED TO SETTLE FURTHER SHORT-TERM
LIABILITIES OF THE COMPANY AND THE MINE
* OPERATOR IS CONFIDENT THAT IT WILL BE ABLE TO FULFILL THE
PLAN
IN THE NEXT FEW WEEKS AND MONTHS
* PROVIDED THE OPERATOR'S EXPECTATIONS ARE MET, ONGOING
OBLIGATIONS FROM RENTAL PAYMENTS CAN BE SETTLED AND PLAN OF SALE
IN 2021 WILL BE PURSUED
Source text for Eikon: ID:nEQ4HKHMPa