Feb 14 (Reuters) - AGL Energy Ltd AGL.AX :
* OUTAGE AT LOY YANG A POWER STATION ON 13 FEBRUARY 2024
* TWO UNITS HAVE RETURNED TO SERVICE AT LOY YANG A POWER
STATION
IN VICTORIA
* DUE TO TRANSMISSION LINES BEING DAMAGED BY SIGNIFICANT
STORM
ACTIVITY, ALL 4 UNITS AT LOY YANG A POWER STATION TRIPPED &
OFFLINE YESTERDAY
* EXPECTED REMAINING UNITS AT LOY YANG A POWER STATION WILL
BE
PROGRESSIVELY AND SAFELY RETURNED TO SERVICE OVER NEXT 24 HOURS
Source text for Eikon: ID:nASX7jkNjb