March 10 (Reuters) - ArcelorMittal SA MT.LU:
TO LAUNCH MAINTENANCE WORK AT TWO PRIMARY STEEL PRODUCTION PLANTS IN FRANCE
MAINTENANCE WORK AT ITS TWO PRIMARY STEEL PRODUCTION PLANTS IN FRANCE, DUNKIRK AND FOS, FOR A TOTAL INVESTMENT OF OVER 270 MILLION EUROS
MAINTENANCE WORK AT DUNKIRK REPRESENTS AN INVESTMENT OF 254 MILLION EUROS
AT ARCELORMITTAL'S DUNKIRK SITE, WORK WILL BE CARRIED OUT IN THE 2ND QUARTER
AT ARCELORMITTAL'S DUNKIRK SITE, WILL RESULT IN A 90-DAY SHUTDOWN OF BLAST FURNACE NUMBER 4
MAINTENANCE WORK COST AT FOS-SUR-MER TO AMOUNT TO 18.3 MILLION EUROS
AT ARCELORMITTAL'S FOS-SUR-MER SITE, BLAST FURNACE IS SCHEDULED TO BE RESTARTED IN THE FIRST HALF OF 2026
Further company coverage: MT.LU
(Gdansk Newsroom)