June 12 (Reuters) - Ascendant Resources Inc ASND.V :
* Ascendant Resources provides May production & exploration
update
* Ascendant Resources Inc - milled production for month was
50,597 tonnes, an average of 1,687 tonnes per day.
* Ascendant Resources Inc - company's El Mochito mine in
Honduras hoisted 46,833 tonnes of ore in month of May, an
average of 1,511 tonnes per day
* Ascendant Resources Inc - first of three trucks ordered in
March is now on site and currently being reassembled underground
* Ascendant Resources Inc - a second truck is expected to
arrive in late June with a third in early July
Source text for Eikon: ID:nCCNFK7Tka
Further company coverage: ASND.V