Aug 1 (Reuters) - Aspen (Group) Holdings Ltd ASPE.SI :
* ASPEN GLOVE SDN. ON 28 JULY GOT ADJUDICATION DECISION IN
RELATION TO TIALOC'S CLAIM AGAINST IT
* AGSB SHALL WITHIN SEVEN DAYS OF RECEIPT OF ADJUDICATION
DECISION
PAY TO TIALOC SUM OF 84.3 MILLION RGT
* AGSB SHALL WITHIN SEVEN DAYS OF RECEIPT OF ADJUDICATION
DECISION
PAY TO TIALOC FINANCING CHARGES OF 6.3 MILLION RGT
* ESTIMATED LOSS ARISING FROM ADJUDICATION DECISION WILL BE
10
MILLION RGT FOR FY ENDED 30 JUNE
* ADVERSE IMPACT IS EXPECTED ON FINANCIAL POSITION OF GROUP
FOR
FINANCIAL YEAR ENDING 30 JUNE 2024
* AGSB HAD, ON 25 JULY 2023, SUBMITTED A REQUEST FOR
ARBITRATION
* REQUEST FOR ARBITRATION IN RELATION TO AGSB'S CROSS-CLAIM
AGAINST TIALOC
* AGSB IS CLAIMING AN AGGREGATE AMOUNT OF 149.3 MILLION RGT
AGAINST TIALOC
Source text for Eikon: ID:nSN37Q01p
Further company coverage: ASPE.SI
((Reuters.Briefs@thomsonreuters.com;))