RNS Number : 0581M Aura Energy Limited 13 November 2024
13 November 2024
ASX Trading Halt
Aura Energy Limited (ASX: AEE, AIM: AURA) ('Aura' or the 'Company')
announces that the Company has requested the Australian Securities
Exchange ("ASX") to halt trading in its shares quoted on the ASX in accordance
with ASX Listing Rule 17.1, pending a project update announcement from the
Company.
The Company expects trading in its shares to resume on the ASX either when the
expected announcement is made, or upon market open on the ASX on 15 November
2024, whichever is the earlier, and will provide the market with an update in
due course.
Trading in the Company's ordinary securities will continue to trade as normal
on AIM, a market operated by the LSE, during this period.
The full version of the ASX announcement can be seen here:
http://www.rns-pdf.londonstockexchange.com/rns/0581M_1-2024-11-13.pdf
(http://www.rns-pdf.londonstockexchange.com/rns/0581M_1-2024-11-13.pdf)
ENDS
Aura Energy Ltd has approved this announcement.
This Announcement contains inside information for the purposes of the UK
version of the market abuse regulation (EU No. 596/2014) as it forms part of
United Kingdom domestic law by virtue of the European Union (Withdrawal) Act
2018 ('UK MAR').
For further information, please contact:
Andrew Grove Paul Ryan SP Angel Corporate Finance LLP
Managing Director and CEO Sodali & Co Nominated Advisor and Broker
Aura Energy Limited Investor & Media Relations David Hignell
agrove@auraee.com (mailto:Agrove@auraee.com) paul.ryan@sodali.com (mailto:paul.ryan@sodali.com) Adam Cowl
+61 414 011 383 +61 409 296 511 Devik Mehta
Grant Barker
+44 203 470 0470
About Aura Energy (ASX: AEE, AIM: AURA)
Aura Energy is an Australian-based mineral company with major uranium and
polymetallic projects in Africa and Europe.
The Company is focused on developing a uranium mine at the Tiris Uranium
Project, a major greenfield uranium discovery in Mauritania. 2024 FEED
Study 1 and Updated Production Target 2 demonstrated Tiris to be a near-term
low-cost 2Mlbs U(3)O(8) pa future uranium mine with a 25-year mine life with
excellent economics and optionality to expand to accommodate future resource
growth.
Aura plans to transition from a uranium explorer to a uranium producer to
capitalise on the rapidly growing demand for nuclear power as the world shifts
towards a decarbonised energy sector.
Beyond the Tiris Project, Aura owns 100% of the Häggån Project in Sweden.
Häggån contains a global-scale 2.5Bt vanadium, sulphate of potash ("SOP") 3
and uranium 4 resource. Utilising only 3% of the resource, a 2023 Scoping
Study 5 outlined a 17-year mine life based on mining 3.5Mtpa.
Disclaimer Regarding Forward-Looking Statements
This ASX announcement (Announcement) contains various forward-looking
statements. All statements other than statements of historical fact are
forward-looking statements. Forward-looking statements are inherently subject
to uncertainties in that they may be affected by a variety of known and
unknown risks, variables and factors which could cause actual values or
results, performance or achievements to differ materially from the
expectations described in such forward-looking statements. The Company does
not give any assurance or guarantee that the anticipated
results, performance or achievements expressed or implied in those
forward-looking statements will be achieved.
The Company has concluded that it has a reasonable basis for providing the
forward-looking statements and production targets included in this
announcement and that material assumptions remain unchanged. The detailed
reasons for this conclusion are outlined throughout this announcement, and in
the ASX Releases, "Scoping Study Confirms Scale and Optionality of Häggån",
5 September 2023; "Aura's Tiris FEED Study returns Excellent Economics" 28
February 2024; "Tiris Uranium Project Enhanced Definitive Feasibility Study",
29 March 2023 and "Updated Production Target improves economics at Tiris
Uranium Project" 11 September 2024.
ASX and JORC Related Disclosures
Mineral Resources
The information on Mineral Resources for the Tiris Uranium Project in this
report is extracted from the ASX release on 12 June 2024 titled "Aura
increases Tiris Mineral Resources by 55% to 91.3Mlbs".
The information on Mineral Resources for the Tiris Uranium Project in this
report is extracted from the ASX release on 10 October 2019 titled "Häggån
Battery Metal Project Resource Upgrade Estimate Successfully Completed". These
reports can be viewed at
https://auraenergy.com.au/investor-centre/asx-announcements
(https://auraenergy.com.au/investor-centre/asx-announcements) .
The company confirms that it is not aware of any new information or data that
materially affects the information included in the original market
announcement and, in the case of estimates of Mineral Resources or Ore
Reserves, that all material assumptions and technical parameters underpinning
the estimates in the relevant market announcement continue to apply and have
not materially changed. The company confirms that the form and context in
which the Competent Person's findings are presented have not been materially
modified from the original market announcement.'
Production Targets
The information on Production Targets for the Tiris Uranium Project in this
report is extracted from the ASX release on 11 Sept 2024 titled "Updated
Production Target Improves Economics at Tiris". This report can be viewed at
https://auraenergy.com.au/investor-centre/asx-announcements
(https://auraenergy.com.au/investor-centre/asx-announcements) .
The company confirms that it is not aware of any new information or data that
materially affects the information included in the original market
announcement and that all material assumptions and technical parameters
underpinning the estimates in the relevant market announcement continue to
apply and have not materially changed.
1 ASX and AIM Release: 28 Feb 2024 - FEED study confirms excellent economics
for the Tiris Uranium Project
2 ASX and AIM Release: 11 Sept 2024 - Updated Production Target improves
economics at Tiris Uranium Project
3 ASX and AIM Release: 10 Oct 2019 - Häggån Battery Metal Project Resource
Upgrade Estimate
4 ASX and AIM Release: 22 Aug 2012 - Outstanding Häggån Uranium Resource
expands to 800 million pounds
5 ASX and AIM Release: 5 Sept 2023 - Scoping Study Confirms Scale and
Optionality of Häggån
This information is provided by RNS, the news service of the London Stock Exchange. RNS is approved by the Financial Conduct Authority to act as a Primary Information Provider in the United Kingdom. Terms and conditions relating to the use and distribution of this information may apply. For further information, please contact
rns@lseg.com (mailto:rns@lseg.com)
or visit
www.rns.com (http://www.rns.com/)
.
RNS may use your IP address to confirm compliance with the terms and conditions, to analyse how you engage with the information contained in this communication, and to share such analysis on an anonymised basis with others as part of our commercial services. For further information about how RNS and the London Stock Exchange use the personal data you provide us, please see our