May 6 (Reuters) - Bluenord ASA BNOR.OL :
* UPDATE ON TYRA REDEVELOPMENT PROJECT
* INVESTIGATION CONFIRMS TECHNICAL ISSUE RELATES TO
TRANSFORMER
DELIVERING POWER TO INTERMEDIATE PRESSURE (IP) GAS COMPRESSOR
* OPERATOR, TOTALENERGIES, HAS CONCLUDED THAT TRANSFORMER
FOR IP
GAS COMPRESSOR NEEDS TO BE REPAIRED WHICH WILL IMPACT TIMING OF
RAMP-UP TO MAXIMUM TECHNICAL CAPACITY
* REPAIR WORK IS ONGOING AND A DEDICATED TEAM IS IN PARALLEL
DEVELOPING OPTIONS TO PARTIALLY RESUME GAS EXPORT FROM TYRA II
AS SOON AS POSSIBLE
* OPERATOR EXPECTS TYRA II TO HAVE REACHED FULL TECHNICAL
CAPACITY
IN Q4 2024
* OPERATOR EXPECTS FROM TIME TO TIME MINIMAL RESIDUAL EXPORT
VOLUMES FLOWING VIA TYRA HUB FOR ENTERING EXPORT SYSTEM DURING
MAY, JUNE