COPENHAGEN, May 6 (Reuters) - Production at Denmark's
Tyra natural gas field will only reach its plateau production
level in the fourth quarter this year instead of mid-year due to
technical issues with a power transformer, operator
TotalEnergies TTEF.PA said on Monday.
BlueNord BNOR.OL , a partner in the TotalEnergies-operated
development, has put its production guidance between the second
and fourth quarter this year under review as a result of the
delay, it said in a separate statement on Monday.
BlueNord expects to give an update on its revised
guidance in connection with its first quarter earnings report on
Tuesday, it added.