Denmark's Tyra gas field ramp-up delayed by three weeks

OSLO, Dec 19 (Reuters) - The ramp-up of production at
Denmark's Tyra gas field has been delayed by three weeks due to
minor operational challenges and adverse offshore weather
conditions, operator Totalenergies  TTEF.PA  and its partner
Bluenord  BNOR.OL  said on Thursday.
    The field is now scheduled to hit plateau production by Jan.
21, while it had previously been expected to do so on Dec. 31,
the companies said.

 (Reporting by Terje Solsvik, editing by Anna Ringstrom 
)