Dec 28 (Reuters) - Build King Holdings Ltd 0240.HK :
* Noted press reports today in relation to the group's shatin central link -diamond hill station joint venture project
* Says expects that the proposed withdrawal will not have any material impact on the financial position of the group
* Build king -group confirms that the execution of the project (which is now over 50% completion and is due for completion in 2017) remains on schedule
* Says group has received its share of distribution from the joint venture amounting to hk$27 million in total
* Noted press reports today in relation to proposed withdrawal of group's joint venture partner, sembawang engineers and constructors due to financial difficulties
* Clarifies proposed withdrawal of SEC is subject to consent of mtr corporation limited
* Source text for Eikon ID:nHKS1rQkFC
((For more news, please click here 0240.HK ))
((Bengaluru Newsroom; +91 80 6749 1130))