April 25 (Reuters) - Cadeler A/S CADLR.OL :
* SIGNS TWO CONTRACTS WITH ØRSTED AND ENTERS NEW STRATEGIC
DIRECTION IN FOUNDATIONS SPACE
* TODAY, CADELER HAS SIGNED TWO CONTRACTS WITH ØRSTED FOR
HORNSEA
3 OFFSHORE WIND FARM IN UK
* FOUNDATIONS CONTRACT WILL POSITION COMPANY IN COMPLETELY
NEW AND
STRATEGIC BUSINESS AREA AS FULL-SERVICE T&I PROVIDER IN
FOUNDATIONS SPACE
* TOGETHER TWO CONTRACTS CONSTITUTE A VERY LARGE CONTRACT
AWARD
* FIRST CONTRACT IS FOR TRANSPORTATION AND INSTALLATION
(T&I) OF
ALL MONOPILE TYPE FOUNDATIONS ON PROJECT
* FOUNDATIONS CONTRACT WILL POSITION COMPANY IN A COMPLETELY
NEW
AND STRATEGIC BUSINESS AREA AS A FULL-SERVICE T&I PROVIDER IN
FOUNDATIONS SPACE
* PROJECT IS EXPECTED TO BEGIN IN Q1/2026 AND FINISH BY END
OF
YEAR
* SECOND CONTRACT IS FOR INSTALLATION OF AROUND HALF OF WIND
TURBINE GENERATORS (WTGS) REQUIRED
* TURBINE PROJECT IS FORECAST TO BEGIN JUST AS FOUNDATIONS
PROJECT
IS COMPLETED AROUND Q4/2026 AND IS EXPECTED TO FINISH IN 2027
* CADELER WILL MAKE USE OF ONE OF ITS TWO NEWBUILD X-CLASS
VESSELS
Source text for Eikon: ID:nObiBqbcRa
Further company coverage: CADLR.OL
(Gdansk Newsroom)
((gdansk.newsroom@thomsonreuters.com; +48 58 769 66 00;))