Aug 10 (Reuters) - Centerra Gold Inc CG.TO :
* CENTERRA GOLD REPORTS SECOND QUARTER RESULTS
* Q2 ADJUSTED LOSS PER SHARE $0.12
* Q2 LOSS PER SHARE $0.01 INCLUDING ITEMS
* GOLD PRODUCTION FOR QUARTER OF 42,728 OUNCES, SOLELY FROM
MOUNT
MILLIGAN MINE
* COPPER PRODUCTION FOR QUARTER OF 17.4 MILLION POUNDS
* GOLD ROOM OPERATIONS AT ADR PLANT AT ÖKSÜT MINE REMAIN
SUSPENDED
SINCE EARLY MARCH DUE TO MERCURY DETECTED IN GOLD ROOM
* INITIATING SUSPENSION OF ÖKSÜT MINE'S STACKING AND
LEACHING
OPERATIONS ON AUGUST 10, 2022
* ALL OF COMPANY'S PREVIOUSLY ISSUED 2023 GUIDANCE HAS BEEN
WITHDRAWN AND SHOULD NOT BE RELIED UPON
* MOUNT MILLIGAN MINE 2022 GOLD AND COPPER PRODUCTION
REMAINS ON
TRACK
* CENTERRA GOLD - ON MARCH 18, ANNOUNCED THAT IT HAD
SUSPENDED
GOLD DORÉ BAR PRODUCTION AT ÖKSÜT MINE DUE TO MERCURY DETECTED
IN GOLD ROOM AT ADR PLANT
* AT THAT POINT, MINING, STOCKPILING, CRUSHING, STACKING AND
LEACHING ACTIVITIES CONTINUED AT ÖKSÜT MINE
* CAPITAL COST OF MERCURY ABATEMENT RETROFIT IS EXPECTED TO
BE $5
MILLION
* REVISED ITS CONSOLIDATED 2022 GOLD PRODUCTION TO BE
BETWEEN
245,000 AND 265,000 GOLD OUNCES
* EXPECTS THAT REFINERY RETROFIT WILL BE COMPLETED IN LATE
2022
* CONTINUES TO CONSIDER ALTERNATIVES TO MONETIZE
GOLD-IN-CARBON
INVENTORY PRIOR TO FULL RESTART OF GOLD ROOM AT ADR PLANT
* CENTERRA GOLD - ON AUG 9, MET WITH MINISTRY OF ENVIRONMENT
WHICH
DID NOT APPROVE REQUEST TO USE MORE ACTIVATED CARBON THAN
PERMITTED IN ÖKSÜT MINE'S EIA
* EXPECTS TO SUBMIT NEW PROPOSED EIA APPLICATION FOR ÖKSÜT
MINE BY
END OF AUGUST