Sept 18 (Reuters) - Centrex Ltd CXM.AX :
* ARDMORE OPERATIONS UPDATE
* AS OF 1 OCT 23, FOR NEXT FOUR MONTHS CO EXPECTS TO MINE
30,000
TONNES OF ORE PER MONTH FOR ARDMORE MINE
* ONCE COMMISSIONED IN OCTOBER 23, NEW CRUSHING CIRCUIT AT
ARDMORE
MINE IS EXPECTED TO REDUCE TOTAL CRUSHING COSTS BY 60%
* CO HAS ENTERED INTO FINANCING LEASE AGREEMENT TO PURCHASE
NEW
A$4.4 MILLION CRUSHING & SCREENING CIRCUIT
* CO REMAINS ON SCHEDULE TO EXPORT OVER 50,000 TONNES OF
BENEFICIATED CONCENTRES DURING FIRST SIX MONTHS OF THIS FY FOR
ARDMORE MINE
* COMPANY IS TARGETING UP TO 440,000 TONNES OF BENEFICIATED
CONCENTRATE FOR 2024 CALENDAR YEAR