Czechs to extend lifespan of second nuclear power plant by 20 years (updated)
UPDATE 1-Czechs to extend lifespan of second nuclear power plant by 20 years Updates with quote, details from paragraph 4
PRAGUE, July 14 (Reuters) - The Czech Republic plans to extend the lifespan of both units at its Temelin nuclear power plant by 20 years to 2080 and 2082 respectively, Industry Minister Karel Havlicek said on Tuesday.
The Czech Republic and its main state-owned power company CEZ CEZP.PR are looking to rely more on nuclear power in the coming decades to meet an expected rise in electricity consumption.
Earlier this year, officials said the lifespan of the four units of the only other Czech nuclear power plant, Dukovany, could be extended by 20 years to 2065-2067.
"Extending the operation of Czech nuclear power plants to 80 years is a logical step," Havlicek said, adding it was the right move to start investing to enable long-term operation.
Plans to expand nuclear power also include adding two new 1,200 MW units at Dukovany and launching small modular reactors in the future.
Temelin was put into operation in 2000-2002 and over the years has increased output to 2,172 MW from an original 1,962 MW due to modernisation work. Dukovany, launched earlier, has seen a similar rise in output, to a total 2,048 MW.
Havlicek and CEZ Chief Executive Daniel Benes said investment in the Temelin extension would total between 5 billion and 6 billion crowns ($281.66 million) a year.
France and some other countries have extended the lifespan of nuclear plants as they look to secure sufficient supplies after the gradual end of fossil fuels.
The Czech Republic depends mostly on nuclear and coal plants for electricity production, with coal units expected to be phased out by around 2030, although the current government has been keen to keep some coal capacity running to ensure energy security.
($1 = 21.3020 Czech crowns)