Brief: Channel Infrastructure Says Permanent Decommissioning Of Refinery Process In Conversion Project Completed
July 19 (Reuters) - Channel Infrastructure NZ Ltd
CHI.NZ :
* PERMANENT DECOMMISSIONING OF REFINERY PROCESS IN
CONVERSION
PROJECT AT PLANT COMPLETED DURING QUARTER
* REMAINING 45 MILLION LITRES OF JET PRIVATE STORAGE
CAPACITY TO
BE COMMISSIONED DURING Q3, INCREASING MARSDEN CAPACITY TO 280ML
* FOR SIX MONTHS TOTAL THROUGHPUT WAS 1,630 MILLION LITRES
* TERMINAL AND PIPELINE THROUGHPUTS 821 MILLION LITRES IN Q2
2023,
UP 25% THAN Q2 2022
Further company coverage: CHI.NZ
((Reuters.Briefs@thomsonreuters.com;))
Recent news on Channel Infrastructure NZ
See all newsNew Zealand's Channel Infrastructure falls on trading ex-dividend
Brief: Channel Infrastructure NZ Signs New Jet And Diesel Storage At Marsden Point
Brief: Channel Infrastructure NZ Says It Expects FY26 EBITDA Of NZ$103-108 Million
Brief: Channel Infrastructure NZ Logs Qtrly Total Fuel Throughput 802 Mln Litres
Brief: Channel Infrastructure NZ Enters Into Agreement For Sale, Removal Of Fully Decommissioned CCR Platformer Unit