Dec 21 (Reuters) - China Gold International Resources Corp Ltd CGG.TO :
* China gold international announces jiama mine expansion update and revises
2015 copper production guidance
* Says the company aims to restart the commissioning of stage one in the second
half of 2016
* Says revises its 2015 copper production guidance to 37.5 million pounds, a
21% increase from the 2014
* Construction of stage two is under way and is expected to be completed in the
second half of 2016
* Schedule of commissioning stage one of phase II expansion at jiama mine by Q4
was deferred due to defects
* Source text for Eikon ID:nCCNbXDJ09
* Further company coverage CGG.TO
((Bengaluru Newsroom; +1 646 223 8780))