Feb 23 (Reuters) - CFE NV CFEB.BR :
* PARKWIND SELECTS DEME OFFSHORE FOR FOUNDATION EPCI
CONTRACT AT
ARCADIS OST I
* DEME OFFSHORE HAS BEEN AWARDED A SUBSTANTIAL ENGINEERING,
PROCUREMENT, CONSTRUCTION AND INSTALLATION (EPCI) CONTRACT
* PRODUCTION OF THE MONOPILE FOUNDATIONS WILL START IN 2021,
WHILE
THE INSTALLATION CAMPAIGN IS PLANNED TO START BEFORE THE SUMMER
2022
* NEXT-GENERATION XXL MONOPILES WILL BE THE LARGEST EVER
INSTALLED
IN EUROPE WITH A WEIGHT OF AROUND 2,000 TONNES EACH
* ARCADIS OST 1 IS SCHEDULED TO BE FULLY COMMISSIONED IN
2023
* A ‘SUBSTANTIAL’ CONTRACT REFERS TO A CONTRACT WITH A VALUE
OF
EUR 150 MILLION - EUR 300 MILLION
Source text for Eikon: ID:nNDL6VX6lL
Further company coverage: CFEB.BR
(Gdansk Newsroom)