SINGAPORE, Sept 15 (Reuters) - China Oil & Gas Pipeline
Network Corporation, or PipeChina, said on Friday it has started
building a second trunk line connecting gas fields in southwest
China with the east coast capable of carrying 20 billion cubic
meters (bcm) of natural gas a year.
The pipeline will originate in the southwestern province of
Sichuan and with a total length of 4,269 km (2,653 miles) will
join the existing pipeline grid that crisscrosses China,
eventually reaching regasification terminals in Zhejiang and
Fujian provinces on the east coast, PipeChina said on its
official WeChat platform.
The new project adds on to the existing Sichuan-to-East line
that began pumping gas in 2010 from gas fields in Dazhou in
Sichuan province to Shanghai and currently transports 15 bcm of
gas annually.
The new line will be built in phases. Under the first stage
PipeChina will lay a 1,576-km western section that will also
include 12 branches, crossing the Chongqing municipality and
provinces of Sichuan and Hubei.
PipeChina did not specify when the whole project will be
completed or give the size of investment.
The additional 20 bcm of annual natural gas supply would cut
carbon dioxide (CO2) emissions by more than 29 million tons a
year versus the equivalent use of coal, PipeChina said.
(Reporting by Beijing newsroom and Chen Aizhu; Editing by
Christian Schmollinger)