Sept 24 (Reuters) - Enertronica SpA ENER.MI :
* ANNOUNCED ON FRIDAY TWO CHANGES WITH RESPECT TO ORDER
PIPELINE
PREVIOUSLY COMMUNICATED TO MARKET
* SAID THAT CONSTRUCTION OF A PHOTOVOLTAIC PLANT IN SPAIN
FOR A
CAPACITY OF ABOUT 120 MW WILL NOT BE REALIZED
* 120 MW PHOTOVOLTAIC PLANT CONTRACT, WHOSE ESTIMATED VALUE
WAS
AROUND EUR 14 MILLION, WAS COMMUNICATED TO MARKET ON AUG. 1,
2017
* CONFIRMS ORDERS FOR SUPPLY OF PHOTOVOLTAIC INVERTERS FOR
200MW
WITH A VALUE OF ABOUT 10 MILLION EURO SIGNED BY ELETTRONICA
SANTERNOM
* ADDS THAT ACTIVITIES RELATED TO IMPLEMENTATION OF
PHOTOVOLTAIC
INVERTERS HAVE SHIFTED ABOUT 6 MONTHS AND THE EFFECTS ON 2018
RESULTS WILL BE LESS EVIDENT THAN INITIALLY ESTIMATED
* ELETTRONICA SANTERNO SIGNED CONTRACT IN SOUTH AFRICA FOR
THE
SUPPLY OF ABOUT 120 MW OF PHOTOVOLTAIC INVERTERS WORTH C. EUR 10
MILLION THAT WILL BE IMPLEMENTED IN 2018-2019
* SAID CONTRACT IN SOUTH AFRICA HAS NOT BEEN INCLUDED IN
FORECASTS
FOR TURNOVER AND THEREFORE WILL COMPENSATE FOR NON-COMPLETION OF
THE CONTRACT IN SPAIN
* WORKS UNDER CONTRACT SIGNED BY ENERTRONICA INC IN NEVADA
(USA)
FOR CONSTRUCTION OF A PHOTOVOLTAIC PLANT WITH A CAPACITY OF
ABOUT 27 MW ARE COMPLETED HOWEVER CONTRACT SHOWED SOME LOSES
CURRENTLY ESTIMATED AT USD 5 MILLION
* DUE TO CHANGES TO ORDER PIPELINE AND ONGOING NEGOTIATIONS
DECIDED TO SUSPEND APPROVAL PROCESS FOR H1 2018 FINANCIAL
STATEMENTS
* SETS DATE FOR APPROVAL OF ITS H1 FINANCIAL REPORT FOR NOV.
15
* ON NOV. 15 TO ANNOUNCE PROVISIONAL DATE FOR FY 2018
REPORTS
CLOSING AND UPDATE OF BUSINESS PLAN PRESENTED IN MAY 2018
Source text for Eikon: urn:newsml:reuters.com:*:nBIA4C9hbx