Dec 16 (Reuters) - ENKA INSAAT VE SANAYI AS ENKAI.IS :
* ENKA INSAAT SAYS WAERME HAMBURG GMBH ORDERED ENKA – UNIPER
JV ON
DEC.15 FOR EUR 336 MILLION UNDER DRADENAU COMBINED HEAT AND
POWER PLANT PROJECT
* ENKA INSAAT SAYS WITH THE INITIAL WORKS THE TOTAL PROJECT
REACHED TO EUR 341 MILLION
* ENKA INSAAT SAYS PROJECT IS TURNKEY CONSTRUCTION OF
COMBINED
HEAT AND POWER PLANT OF AROUND 180 MW ELECTRIC AND 260 MW
DISTRICT HEATING CAPACITY AT DRADENAU IN HAMBURG
* ENKA INSAAT SAYS ENKA – UNIPER JV IS TO PERFORM
ENGINEERING,
PROCUREMENT, CONSTRUCTION AND COMMISSIONING WORKS
* ENKA INSAAT SAYS THE POWER PLANT IS EXPECTED TO BE
OPERATIONAL
IN DECEMBER 2024