Jan 4 (Reuters) - Equitrans Midstream Corp ETRN.N :
* MOUNTAIN VALLEY PIPELINE, LLC HAS CONTINUED TO MAKE
SIGNIFICANT
FORWARD CONSTRUCTION PROGRESS ON THE MVP PROJECT
* TARGETED MVP PROJECT COMPLETION REMAINS Q1 OF 2024, AT A
TOTAL
PROJECT COST OF APPROXIMATELY $7.2 BILLION
* AS OF JANUARY 2, 2024, MVP JOINT VENTURE HAS COMPLETED
BORING
OPERATIONS AT SIX LOCATIONS
* ALL MAJOR BORING OPERATIONS ARE EXPECTED TO BE COMPLETE BY
EARLY
FEBRUARY 2024
* REGARDING MVP PROJECT’S 9 MAJOR BORE LOCATIONS, AS OF JAN
2,
2024, 77% OF COMBINED TOTAL BORE LENGTH FOR 9 LOCATIONS IS
COMPLETE
Source text for Eikon: ID:
Further company coverage: ETRN.N