Dec 29 (Reuters) - Equitrans Midstream Corp ETRN.N :
* EQUITRANS MIDSTREAM CORP - EXPECTED TO OPERATE MVP
SOUTHGATE AND
OWNED A 47.2% INTEREST IN MVP SOUTHGATE AS OF SEPTEMBER 30, 2023
* EQUITRANS MIDSTREAM CORP - REDESIGNED MVP SOUTHGATE IS
ESTIMATED
TO COST A TOTAL OF APPROXIMATELY $370 MILLION
* EQUITRANS MIDSTREAM CORP - EXPECTS TO FUND ITS
PROPORTIONATE
SHARE THROUGH CAPITAL CONTRIBUTIONS MADE TO MVP JOINT VENTURE
* EQUITRANS MIDSTREAM CORP - TARGETED COMPLETION TIMING FOR
PROJECT IS JUNE 2028, WITH MAJORITY OF CAPITAL SPEND EXPECTED TO
OCCUR IN 2027
* EQUITRANS MIDSTREAM CORP - IN DEC, MVP JOINT VENTURE
ENTERED
INTO PRECEDENT AGREEMENTS WITH EACH OF PSNC AND INVESTMENT GRADE
COUNTERPARTY
Further company coverage: ETRN.N
((Reuters.Briefs@thomsonreuters.com;))