Oct 25 (Reuters) - EREGLI DEMIR VE CELIK FABRIKALARI TAS
EREGL.IS :
* COST OF CONSTRUCTION OF T4TH COKE BATTERY AND
MODERNIZATION OF
SECONDARY PRODUCT FACİLİTİES, IS $268 MILLION
* IT IS PLANNED TO BE COMMISSIONED IN APRIL 2022
* ERDEMIR NEW SINTER PLANT INVESTMENT HAS APPROXIMATE COST
OF $198
MILLION AND IS PLANNED TO BE COMMISSIONED IN JUNE 2022
* 2ND BLAST FURNACE RENOVATION INVESTMENT PROJECT, HAS
PLANNED
COST OF USD 129 MILLION
* 2ND BLAST FURNACE RENOVATION INVESTMENT PLANNED TO BE
COMMISSIONED IN MARCH 2021