Brief: Erdemir Says No.4 Coke Battery Modernization, One Of The Investments Was Completed And Commissioned
May 23 (Reuters) - EREĞLİ DEMİR VE ÇELİK FABRİKALARI EREGL.IS: SAID ON THURSDAY NO.4 COKE BATTERY MODERNIZATION, ONE OF THE INVESTMENTS WAS COMPLETED AND COMMISSIONED ERDEMIR AIMS TO IMPROVE ENVIRONMENTAL PERFORMANCE, REDUCE IMPORTED COKE PURCHASES AND REDUCE COSTS BY INCREASING EFFICIENCY WITH THE NO.4 COKE BATTERY, WHICH HAS A CAPACITY OF 800 THOUSAND TONS/YEAR Source text: nIKA83cpkL Further company coverage: EREGL.IS (Gdansk Newsroom) ((gdansk.newsroom@thomsonreuters.com; +48 58 769 66 00;))