Nov 4 (Reuters) - ERDEMİR EREGL.IS :
* SAID ON THURSDAY TO ESTABLISH PELLETIZING PLANT AFTER
DETECTING
INTENSE MINERALIZATION FOLLOWING DRILLING WORKS IN THE
BINGOL-AVNIK IRON MINE FIELD LICENSED IN THE NAME OF UNIT
ERMADEN
* APPROXIMATE COST OF THIS INVESTMENT, WHICH HAS AROUND IRON
ORE
RESERVE OF 250-300 MILLION TONS, IS $550 MILLION
* PELLETIZING PLANT WITH ANNUAL PELLET PRODUCTION CAPACITY
OF 3.0
MILLION TONS, IS AIMED TO PRODUCE MORE THAN 100 MILLION TONS OF
PELLETS
* EXPECTS PROFIT INCREASE TO BE OBTAINED FROM THE ACTIVITIES
AT
TODAY'S PRICES WILL BE APPROXIMATELY $200-250 MILLION PER YEAR
* EXPECTS RATE OF SELF-SUFFICIENCY IN PELLET TO INCREASE
FROM
25-30% TO 80-85%, AND THE RATE OF SELF-SUFFICIENCY IN TOTAL
FERROUS RAW MATERIALS WILL INCREASE FROM 15-20% TO 40-45%
Source text for Eikon: urn:newsml:reuters.com:*:nIKA8kBHCl
Further company coverage: EREGL.IS
(Gdansk Newsroom)
((gdansk.newsroom@thomsonreuters.com; +48 58 769 66 00;))