Ferro-Alloy Resrcs. - Project Finance Expression of Interest
RNS Number : 0886G
Ferro-Alloy Resources Limited
04 November 2025
THIS ANNOUNCEMENT CONTAINS INSIDE INFORMATION FOR THE PURPOSES OF THE MARKET ABUSE REGULATION (EU) NO. 596/2014 (INCLUDING AS IT FORMS PART OF THE LAWS OF ENGLAND AND WALES BY VIRTUE OF THE EUROPEAN UNION (WITHDRAWAL) ACT 2018 ("MAR").
4 November 2025
Ferro-Alloy Resources Limited
("Ferro-Alloy", the "Group" or the "Company")
Project Finance Expression of Interest, Front End Engineering and Design Terms Agreed and Substantial Capital Cost Savings Identified
Ferro-Alloy Resources Limited (LSE:FAR), the vanadium producer and developer of the large Balasausqandiq vanadium project (the "Project") in Southern Kazakhstan, is pleased to announce significant progress following the completion of the Project's Feasibility Study.
Highlights
· Terms agreed for front-end engineering and design ("FEED") with China National Chemical Engineering Sixth Construction Co., Ltd ("CC6")
· CC6 have provided an indicative construction cost estimate of US$261m (excluding the relatively minor costs of the equipment relating to uranium and molybdenum sorption), that cuts the funding required to get into production to US$311.9m, a 40% reduction compared to the Feasibility Study
· Corresponding enhanced Project internal rate of return ("IRR") of 31% (unlevered, post-tax) and net present value ("NPV") of US$931.6m
· CC6 has received a US$221.8m non-binding conditional loan offer from the Bank of Communication (Hubei) Branch ("BOC Bank"), equating to 85% of the CC6 scope of work
· Potential access to Sinosure, the Chinese insurance and export credit scheme, substantially lowering financing costs
Nick Bridgen, CEO of Ferro-Alloy Resources, said:
"As previously indicated, we have identified substantial capital cost savings that demonstrate the potential to significantly enhance the Project's financial returns. In addition CC6, a company that has vast experience in building plants all over the world with particular expertise in vanadium processing technology, has secured an attractive conditional offer of construction financing for the Project with BOC Bank."
Overview
The Company has agreed terms for the Project's FEED with CC6. CC6 is one of the largest and most experienced engineering and construction companies in the global vanadium industry.
Furthermore, CC6 has provided an indicative construction cost estimate of US$261m ("EPC Cost Estimate") for the engineering, procurement and construction ("EPC") for the Project. In comparison with the equivalent costs included in the Feasibility Study (announced on 13 October 2025) this demonstrates the potential to reduce capital costs by up to US$177m, and would enhance the Project's IRR to 31% (unlevered, post-tax) and NPV to US$931.6m.
The EPC Cost Estimate received from CC6 excludes the relatively minor costs of the equipment relating to uranium and molybdenum sorption, and certain other costs that are not usually included in an EPC estimate such as first-fill consumables, strategic spare parts and other working capital items. The EPC Cost Estimate is a result of 18 months of continuous engagement between CC6 and the Company. These robust indicative returns highlight the compelling economics of the Project, and the opportunity to reduce capital costs significantly utilising the experience of one of the largest EPC contractors in China.
As part of this initiative, CC6 has received a non-binding conditional offer of finance from the Bank of Communication (Hubei) Branch ("BOC Bank") to provide up to US$221.8m of loan finance, equating to 85% of the CC6 scope of work for the EPC. Initial discussions have been held with Sinosure, the Chinese state-owned insurance company which commonly provides loan guarantees for overseas engineering and construction contracts. In the event that a Sinosure guarantee is received, the interest rate on the BOC Bank loan is expected to be relatively low, giving a very much enhanced rate of return to equity investors.
Concurrently, the Company is engaging with strategic investors for equity financing and has received interest from several potential providers.
Financial impact
Although the CC6 EPC Cost Estimate is subject to confirmation after the completion of FEED, the financial impact of using the CC6 EPC Cost Estimate, while leaving all other cash flows as quoted in the Feasibility Study announced on 13 October 2025, would result in the following changes:
| Feasibility Study US$m | CAPEX incorporating CC6 EPC estimate US$m | |
| Capital expenditure (including working capital, strategic spares, owner's costs, insurance etc.) | 490.2 | 313.2 |
| Contingency | 73.5 | 42.4 |
| Pre-production income, less costs | (43.7) | (43.7) |
| Funding required to get into production | 520.0 | 311.9 |
| Net Present Value (after tax, discount rate of 8%) | 748 | 931.6 |
| Project IRR | 22% | 31% |
| Ferro-Alloy Resources Limited | Nick Bridgen (CEO) / William Callewaert (CFO) | info@ferro-alloy.com |
| Shore Capital (Joint Corporate Broker) Panmure Liberum Limited (Joint Corporate Broker) BlytheRay(Financial PR) | Toby Gibbs / Lucy Bowden Scott Mathieson / John More Tim Blythe / Megan Ray / Will Jones | +44 207 408 4090 +44 20 3100 2000 +44 20 7138 3204 Ferro-Alloy@blytheray.com |
Recent news on Ferro-Alloy Resources
See all newsFerro-Alloy Resrcs. - Issue of Equity and Repayment of Bonds
Ferro-Alloy Resrcs. - Interim Results
Brief: Ferro-Alloy Resources Enters Non-Binding MoU With Maglut For MREC Supply
Ferro-Alloy Resrcs. - Replacement: US Strategic RE Separation MoU
RCS - Ferro-Alloy Resrcs. - Release of Investor Q&A via Investor Meet Company