Algoma Steel warns of shipment impact after outage shuts EAF operations
Algoma Steel warns of shipment impact after outage shuts EAF operations Aug 17 (Reuters) - Canadian steelmaker Algoma Steel ASTL.TO said on Monday future shipment volumes could be affected due to an outage at its captive power plant that forced the suspension of operations at its electric arc furnace.
Here are some key details:
Algoma said one turbine unit at its Lake Superior Power facility was taken offline after detecting an abnormal condition, while the remaining units continued operating.
U.S.-listed shares of the company down 5.3% premarket.
The steelmaker expects the electric arc furnace outage to last no more than 21 days as it works with GE Vernova GEV.N to commission a contracted spare turbine at the site.
The company said alternative onsite power arrangements being evaluated with Ontario's Independent Electricity System Operator could allow EAF operations to restart within about 10 days, if approved.
Algoma said finishing and shipping activities were continuing, with no significant impact expected on committed customer deliveries.
The company said it is assessing the outage's duration and related operational and financial impacts and will provide an update once the assessment is complete and a restart timeline for EAF operations is established.
(Reporting by Varun Sahay in Bengaluru; Editing by Shreya Biswas)
((Varun.Sahay@thomsonreuters.com;))
Recent news on GE Vernova
See all newsS&P 500 top and bottom performing stocks at about 12:00 p.m. EDT
Venture Global gains as Wells Fargo turns bullish on AI data center strategy
Brief: GE Vernova Says Songon Plant To Deliver 372 MW For 5 Million Ivorian Homes
Live Markets: Power constraints create new winners in the AI boom
Press Digest: Wall Street Journal - October 16