Gem Diamonds Limited (LSE: GEMD) ("Gem Diamonds" or the "Company" or the "Group") provides the following trading update detailing the Group's operational and sales performance from 1 January 2025 to 30 June 2025 ("H1 2025" or the "Period"). The Company also announces necessary operational changes and cost management measures being implemented in response to continued challenging market conditions and revises its 2025 guidance.
1. H1 2025 Trading update
Highlights:
| · | The highest price achieved in the Period was US$26 441 per carat for a 67.50 carat white diamond. |
| · | Six diamonds sold for more than US$1.0 million each, generating aggregate revenue of US$9.3 million in the Period. |
| · | Four greater than 100 carat diamonds were recovered during the Period, of which three were sold. |
| · | Post period end, a 250 carat Type II white diamond was recovered,however the quality is such that it is expected to yield a relatively low polished outcome. |
| · | Following the Company's application to relinquish the Ghaghoo mining license, the license was officially cancelled, and the mine site was formally handed back to the Government of Botswana during the Period. |
| H1 2025 | H1 2024 | % Change | |
| Waste tonnes stripped | 1 698 817 | 3 163 476 | -46% |
| Ore tonnes treated | 2 504 001 | 2 542 114 | -1% |
| Satellite pipe contribution (tonnes) | 802 135 | 1 110 647 | -28% |
| Carats recovered | 47 125 | 55 873 | -16% |
| Grade recovered (cpht) | 1.88 | 2.20 | -14% |
| Carats sold | 44 360 | 56 944 | -22% |
| Total value (US$ millions) | 44.7 | 77.9 | -43% |
| US$/carat | 1 008 | 1 366 | -26% |
| · | Mining activities:The mine will continue to operate both plants at existing treatment volumes (c.5.0 million tonnes per annum). An additional 0.5 million tonnes of high value Satellite pipe material have been made accessible to mine and process during H2 2025. Waste mining volumes in both the Main and Satellite pits have been reduced to a minimum for an initial 12-month period without compromising the longer-term life of mine plan. |
| · | Workforce Rationalisation:The Company regrets that a reduction in workforce of approximately 250 employees (representing 20% of the current workforce) may be necessary to align with the scaled-back waste mining operations and other necessary operational changes. Engagement with employees and relevant stakeholders has commenced and is ongoing to ensure that the rationalisation process is managed responsibly and transparently. |
| · | Reduction in corporate costs:Further actions are being taken to reduce cash outflow at the corporate office, including temporary salary reductions for Board, Executives and management personnel. The Company is considering awarding shares in lieu of salary to partially compensate the Executives and management personnel for the reduction in cash remuneration and to further align the interests of key management with shareholders. |
| FY 2025 Revised Guidance | FY 2025 Original Guidance | |
| Waste tonnes mined (Mt) | 1.8 - 2.0 | 5.0 - 5.5 |
| Ore treated (Mt) | 4.9 - 5.1 | 4.9 - 5.1 |
| Satellite pipe ore treated (Mt) | 1.2 - 1.4 | 0.8 - 1.0 |
| Carats recovered (Kct) | 87 - 90 | 87 - 90 |
| Carats sold (Kct) | 84 - 87 | 86 - 89 |
| Direct cash costs (before waste) per tonne treated (Maloti) | 225 - 240 | 245 - 260 |
| Operating costs per tonne treated1 (Maloti) | 295 - 310 | 345 - 360 |
| Mining waste cash costs per tonne of waste mined (Maloti) | 60 - 70 | 60 - 70 |
| Total capex(US$ million) | 4.0 - 5.0 | 4.0 - 6.0 |
Recent news on Gem Diamonds
See all newsUK's Gem Diamonds H1 revenue rises 32% on higher prices
Brief: Gem Diamonds H1 Pretax Profit USD 3.1 Million
Gem Diamonds Limited - Half Year 2026 Results
Gem Diamonds Limited - Notification of Half Year 2026 Results
Brief: Gem Diamonds Says All Operational And Financial Metrics Trending Within 2026 Guidance