============
Genel Energy PLC (GENL)
Genel Energy PLC: Trading and operations update
11-May-2023 / 07:00 GMT/BST
══════════════════════════════════════════════════════════════════════════
11 May 2023
Genel Energy plc
Trading and operations update
Genel Energy plc ('Genel' or 'the Company') issues the following trading
and operations update relating to Q1 2023, ahead of the Company's Annual
General Meeting ('AGM'), which is being held today.
Paul Weir, Chief Executive of Genel, said:
“The prolonged closure of the Iraq-Turkey pipeline is very disappointing
and, although there continues to be speculation regarding the timing of
resumption of exports, we cannot predict with any certainty when exports
will recommence. In anticipation of exports resuming we are seeking
clarity on future arrangements and a mechanism in place for regular and
predictable payments going forward.
Delays in payments and the suspension of exports have resulted in
significant cash generation being deferred and we are scaling back our
planned activity accordingly. We continue to reduce costs so that the size
and shape of the organisation matches the needs of the business.
Our financial position is robust, and we remain focused on using our
significant liquidity to add new assets to the portfolio that will fund
the long-term payment of our established dividend.”
Q1 2023
• Zero lost time incidents in 2023, with over four million hours worked
since the last incident
• Net production of 26,000 bopd in Q1 2022 (30,520 bopd in Q1 2022)
• Pending approval at the AGM today, a dividend distribution of 12¢
(9.6588 pence) per share will be paid on 19 May 2023
• $61 million of cash proceeds were received from the Kurdistan Regional
Government (‘KRG’) in Q1 2023, relating to August and September 2022
• Capital expenditure of $24 million in Q1 2023, of which $21 million
was cost recoverable spend at Tawke and Taq Taq
• Cash of $496 million at 31 March 2023 ($495 million at 31 December
2022)
• Net cash under IFRS of $229 million at 31 March 2023 ($228 million at
31 December 2022)
◦ Total debt of $274 million at 31 March 2023 ($274 million at 31
December 2022)
2023 OUTLOOK AND GUIDANCE
• Due to the closure of the Iraq-Turkey Pipeline on 25 March 2023 and
resulting impact on production, Genel’s production guidance of
27-29,000 bopd is no longer valid. New guidance will be issued once
the pipeline reopens and investment plans are confirmed
• Genel now expects capital expenditure to be below $100 million
(previous guidance $100-125 million)
• Payments totalling $80 million are outstanding relating to production
from October 2022 to January 2023, with $110 million of total sales
invoices submitted up to and including March 2023
PRODUCTION BUSINESS
• Tawke PSC (25% working interest)
◦ Gross production averaged 93,880 bopd in Q1 2023 (106,470 bopd in
Q1 2022), due to planned well intervention operations temporarily
constraining overall production
◦ Given the uncertain timing of export resumption and the delays in
payments, spend at the Tawke licence has been scaled back, with
the number of active rigs to drop from four at the start of 2023
to none in H2 2023
◦ Five wells were completed and another three wells spudded in Q1
2023, with Tawke licence drilling to end in May
• Sarta (30% working interest and operator)
◦ Gross production averaged 3,160 bopd in Q1 2023 (5,590 bopd in Q1
2022)
◦ As previously stated, Genel’s focus is on making ongoing
production from Sarta profitable
• Taq Taq PSC (44% working interest and joint operator)
◦ Gross production averaged 3,610 bopd in Q1 2023 (5,070 bopd in Q1
2022)
◦ Taq Taq continues to produce into storage, with around one week
of storage capacity remaining
PRE-PRODUCTION BUSINESS
• Somaliland
◦ Preparation continues for the drilling of the Toosan-1 well on
the highly prospective SL10B13 block (51% working interest and
operator)
◦ The Toosan prospect contains stacked Mesozoic reservoir
objectives, with multiple individual prospective resource
estimates each ranging from 100 to 200 MMbbls
◦ Civil work at the wellsite is set to get underway shortly, and
the Environmental, Social and Health Impact Assessment is nearing
completion
◦ Genel continues to target a spud date in H1 2024, acknowledging
the challenges of operating in such a frontier area with limited
existing infrastructure
• Morocco
◦ The farm-out programme on the Lagzira block (75% working interest
and operator) is ongoing
ESG
• Genel’s 2022 Sustainability Report has been issued today, detailing
our environmental performance and the positive impact that we strive
to have on the communities in which we operate. Highlights include:
◦ Zero LTIs across all Genel operations with 3 million hours worked
incident free
◦ Zero waste to landfill from operations at Sarta, with 91%
recycled
◦ Solar panel and battery storage unit operational at Sarta
◦ Improvement in both CDP climate change and water security score
ARBITRATION
• The London-seated international arbitration regarding Genel’s claim
for substantial compensation from the KRG following the termination of
the Miran and Bina Bawi PSCs is progressing. The trial remains
scheduled for February 2024
-ends-
For further information, please contact:
Genel Energy
+44 20 7659 5100
Andrew Benbow, Head of Communications
Vigo Consulting
+44 20 7390 0230
Patrick d’Ancona
This announcement includes inside information.
Notes to editors:
Genel Energy is a socially responsible oil producer listed on the main
market of the London Stock Exchange (LSE: GENL, LEI:
549300IVCJDWC3LR8F94). The Company is one of the largest London-listed
independent hydrocarbon producers, with an asset portfolio that positions
us well for a future of fewer and better natural resources projects. Genel
has low-cost and low-carbon production from the Kurdistan Region of Iraq,
and a committed dividend programme that is material and sustainable. Genel
continues to seek opportunities to add new resilient and cash-generative
assets to its portfolio, with the goal of progressing its dividend in the
long-term. For further information, please refer to 1 www.genelenergy.com
══════════════════════════════════════════════════════════════════════════
Dissemination of a Regulatory Announcement that contains inside
information in accordance with the Market Abuse Regulation (MAR),
transmitted by EQS Group.
The issuer is solely responsible for the content of this announcement.
══════════════════════════════════════════════════════════════════════════
ISIN: JE00B55Q3P39, NO0010894330
Category Code: TST
TIDM: GENL
LEI Code: 549300IVCJDWC3LR8F94
Sequence No.: 242827
EQS News ID: 1630011
End of Announcement EQS News Service
══════════════════════════════════════════════════════════════════════════
2 fncls.ssp?fn=show_t_gif&application_id=1630011&application_name=news&site_id=refinitiv
References
Visible links
1. https://eqs-cockpit.com/cgi-bin/fncls.ssp?fn=redirect&url=3ec46b352f38452116096dbbab51b09e&application_id=1630011&site_id=refinitiv&application_name=news
============