Dec 16 (Reuters) - Getlink SE GETP.PA :
* TECHNICAL INTERRUPTION TO ELECLINK OPERATIONS
* IMPACT OF SUSPENSION OF ACTIVITY DURING FIRST 6 WEEKS OF
2025 IS
ESTIMATED AT APPROXIMATELY EUR 30 MLN
* SUSPENSION OF ACTIVITY UNTIL 31 DECEMBER 2024 WILL HAVE AN
ADDITIONAL COMMERCIAL IMPACT ESTIMATED AT APPROXIMATELY 11
MILLION EUROS
* RE-ENTRY INTO SERVICE OF INTERCONNECTOR IS EXPECTED ON 10
FEBRUARY 2025
* TECHNICAL TESTS CARRIED OUT AHEAD OF REENERGISATION
REVEALED A
SECOND FAULT ON INTERCONNECTOR IN NEARBY AREA
* GROUP EBITDA TARGET RANGE FOR 2024 REMAINS UNCHANGED
* REPAIR WILL REQUIRE DEDICATED WORK (CABLE SECTION
REPLACEMENT
AND REJOINTING OPERATIONS) AND LEAD TO AN ESTIMATED EXTENSION OF
OUTAGE OF 8 WEEKS
Source text: ID:nBw8CT7lva