Aug 30 (Reuters) - Grupa Azoty SA ATTP.WA :
* SAID ON FRIDAY GENERAL CONTRACTOR FOR POLIMERY POLICE
PROJECT
HYUNDAI ENGINEERING CO STARTS PROCEDURE TO CHANGE EPC DEAL
* PROPOSED CHANGES INCLUDE INCREASING CONTRACTOR'S
REMUNERATION BY
TOTAL EUR 127.4 MILLION, EXTENDING PROJECT DEADLINE BY 181 DAYS
AND CHANGING ATTACHMENT TO DEAL SETTING OUT EXTENT OF WORKS
* REASON GIVEN BY CONTRACTOR FOR PROPOSED CHANGES IS
PARTICULARLY
IMPACT OF COVID-19 PANDEMIC ON IMPLEMENTATION OF PROJECT
Source text for Eikon: urn:newsml:reuters.com:*:nEM92cBHJa
Further company coverage: ATTP.WA
(Gdansk Newsroom)