** Shares of graphite and hydrogen producer Hazer Group
HZR.AX fall as much as 11.8% to A$1.080, set for their biggest
intraday percentage loss since Sept 13
** Says there has been a delay to the completion of the
fabrication of the reactor for the Hazer Commercial
Demonstration Project near Perth urn:newsml:reuters.com:*:nASX9Xmyds
** Says expected to delay the planned commissioning of the
Hazer CDP, which is now expected to occur after 1Q 2022.
** Co says it has been advised that a manufacturing flaw has
been identified in the Hazer reactor vessel currently waiting
for heat treatment in China
** Says it anticipates at least an 8 to 12 week delay which
could impact the project schedule significantly
** Stock hits lowest since Dec 6 and is on track to extend
losses to a second straight session
** Stock up ~52.2% this year as of last close
(Reporting by Tejaswi Marthi in Bengaluru)