Picture of Horizonte Minerals logo

HZM Horizonte Minerals News Story

0.000.00%
gb flag iconLast trade - 00:00
Basic MaterialsHighly SpeculativeMicro CapValue Trap

REG - Horizonte Minerals - Q2 2023 Araguaia Construction Update

For best results when printing this announcement, please click on link below:
http://newsfile.refinitiv.com/getnewsfile/v1/story?guid=urn:newsml:reuters.com:20230803:nRSC1957Ia&default-theme=true

RNS Number : 1957I  Horizonte Minerals PLC  03 August 2023

NEWS
RELEASE

3 August 2023

 

HORIZONTE MINERALS PROVIDES Q2-2023 UPDATE

CONSTRUCTION OF ARAGUAIA NICKEL PROJECT NOW 65% COMPLETE

 

HIGHLIGHTS:

·    Araguaia Nickel Project Line 1 construction activities continued to
make good progress with first metal production on-schedule for Q1 2024

-      Strong safety performance, no lost time injuries with close to 3.8
million hours worked

-      Approximately 65% of the overall construction of Araguaia was
completed as of 30 June 2023, with physical site construction 53% complete

-      Several major milestones were achieved during the quarter
including the delivery of the Rotary Kiln and commencement of ore mining

-      US$329 million has been spent on the Araguaia construction out of
the budgeted capital requirement of US$537 million

·    Araguaia Nickel Project Line 2 Feasibility Study ("FS"), which aims
to double nickel production from 14,500 tonnes per annum to 29,000 tonnes per
annum, to be published later this year

·    Liquidity and funding sources of US$344 million as of 30 June 2023

·    Published fourth consecutive standalone Sustainability Report for
2022

·    A recent video of the project progress is available:
https://horizonteminerals.com/uk/en/videos_and_audio/

 

Horizonte Minerals Plc (AIM/TSX: HZM) ("Horizonte" or the "Company") the
nickel company developing two Tier 1 assets in Brazil, reports that it is
continuing to make good progress on the construction of its 100%-owned
Araguaia Nickel Project Line 1 ("Araguaia" or "the Project"). The Company is
targeting first metal in Q1 2024. Management will be hosting a webinar today,
3 August 2023, at 14:00 BST to discuss Araguaia's construction progress.

 

As of 30 June 2023, approximately 65% of the overall Araguaia Line 1
construction programme has been completed, physical site construction was 53%
advanced with ore stockpiling having now commenced following the issuance of
the mining permit during the quarter. Additionally, a major milestone in the
quarter was the safe delivery to site of the rotary kiln, a key long lead
item. The 11 steel sections will now be aligned and welded together before
being lifted into place for final installation on the kiln piers. Off-site,
construction of the 126km, 230kV transmission line is well advanced with over
90% of the pylons erected and 42 km of conductor cable installed. Construction
of the water storage reservoir has commenced. As of 30 June 2023, a total of
US$329 million has been spent on the Araguaia construction out of the budgeted
capital requirement of US$537 million. As at quarter-end, the Company had
total liquidity and funding sources of US$344 million.

 

Jeremy Martin, CEO of Horizonte, commented: "We are pleased with progress to
date at Araguaia Phase 1, with around 65% of the overall project completed as
at quarter-end. We are targeting first metal in Q1 2024.

 

"We are proud to have maintained a strong safety record to date and the safe
delivery of the rotary kiln to site was a significant milestone during the
quarter and a testament to the commitment and dedication of our team.

 

"Whilst the key focus is the construction activities at Araguaia, we are
making good progress on the Line 2 Feasibility Study which is scheduled to be
published later this year. The proposed expansion has the potential to double
the annual nickel production to 29,000 tonnes per year.

 

"With the progress made to date, we remain confident in our ability to deliver
our world-class project in a safe and responsible manner, continuing to move
closer to unlocking the full value of Araguaia, and more broadly across
Horizonte's portfolio of Tier 1 assets, realising our objective of becoming a
low-cost nickel producer."

 

The FS for Horizonte's 100% owned Vermelho project in Brazil, is currently
on-going and is expected to be published in 2024. Vermelho has a high-grade
scalable resource with a long mine life. Given Vermelho's geological
characteristics, the ore has the ability to be processed either through
High-Pressure Acid Leach ("HPAL") or Rotary Kiln Electric furnace ("RKEF")
technologies. As part of the study and driven by the evolving market dynamics,
Horizonte is evaluating the optimal final nickel product that will supply the
critical metals market.

 

Management will be hosting a webinar today, 3 August 2023, at 14:00 BST to
discuss Araguaia's construction progress. Investors and analysts are invited
to access the webinar by registering in advance via the following link:
https://www.investormeetcompany.com/horizonte-minerals/register-investor.
Questions may be submitted at any time during the live presentation. A
recording of the webinar will be available on the Company's website shortly
after its conclusion.

 

 

ARAGUAIA LINE 1 CONSTRUCTION: FIRST METAL ON-SCHEDULE FOR Q1 2024

 

1.      Health, Safety & Wellbeing

The lost-time injury frequency rate ("LTIFR") for Araguaia as at June 30 2023
was 0.00 and the total recordable injury frequency rate ("TRIFR") was 1.03
based on a 12-month rolling average 1  (#_ftn1) . This compares favourably
with a TRIFR of 3.7 for the same period last year but is a decrease in
performance compared to the previous quarter and reflects three restricted
work cases in the quarter where an employee is unable to perform the full
range of normally assigned duties over the course of a day. As the
construction workforce has increased by 18% to over 3,300 people across the
project during this period, Horizonte has continued to focus its efforts on
embedding the critical risk controls within the growing workforce whilst
reinforcing risk management. The Company continues to implement tools to
increase engagement and participation by our contracting partners in our
safety systems and processes. For the project to date, over 5,800 internal
safety audits have been conducted and over 7,500 safety plan observations have
been completed. In the quarter, extensive campaigns on hand safety were
conducted.

 

2.      Construction activities

As seen in Figure 1, good progress has been made across the RKEF processing
site where overall project completion was approximately 65% advanced, with
physical site construction 53% complete and multiple work fronts are active.
Araguaia's Rotary Kiln Electric Furnace flow sheet is designed to produce
14,500 tonne-per-annum of high-grade ferronickel (FeNi). The Araguaia
processing site has also been designed and optimised to allow for the build
out of Line 2 with key fixed infrastructure sized to support both lines,
helping to reduce the overall cost of developing Line 2.

 

Figure 1 - An overview of the Araguaia processing site

 

 

 

Figure 2 shows the ROM pad along with the ROM bin and primary crusher. The
steel structure will house the crusher which is already on site. Ore blended
from the ROM stockpiles, will pass through the primary and secondary crushers
where it will be reduced to less than 80 mm, before being transferred to the
Homogenisation shed.

 

 

Figure 2 - The ROM pad, ROM bin and primary crusher

 

 

Figure 3 shows the roof trusses being installed for the 193m long
Homogenisation shed that will be used to blend the crushed ore. An overhead
tripper conveyor will run the full length of the shed capable of building two
blended stockpiles, one of which will be being built while the other is being
reclaimed. Each stockpile has a capacity of around 18,000t, enough for 3.5
days of furnace feed.

 

 

Figure 3 - The Homogenisation shed

 

 

 

Figure 4 shows the four Rotary Kiln piers, the individual kiln pieces and the
steel erection of the electrostatic precipitator. Having arrived at site in
June following an ~18,000km journey by sea, river and road, the 11 pieces of
the 802 tonne FLSmidth rotary kiln will now be aligned using polar
verification, welded together into four sections before being lifted into
place for final welding and installation on the kiln piers. The kiln itself
was designed and built according to the highest industry-leading standards to
improve efficiency of the reduction process. Features include having the
lowest specific heat loss in its class as well as an integrated electrostatic
precipitator, delivering efficient emission controls thereby having one of
lowest particulate emission levels in the industry.

 

 

Figure 4 - Rotary kiln piers, the individual kiln pieces, the steel erection
of the electrostatic precipitator and the electric arc furnace

 

 

As seen in Figure 5, erection of the steel structure that surrounds the
electric arc furnace continues to make good progress with the 4(th) of 5
floors now erected. This will house all the associated equipment and
infrastructure that is required to operate the furnace within a temperature
range of up to 1,550 (o)C. Erection of the building is through a modular
construction process, lifting large pre-assembled sections of steel work,
including scaffolding and railings, into place. The calcine transfer system,
located on the left-hand side, takes the hot caline from the rotary kiln and
delivers it into the electric arc furnace. From there, the ferronickel will be
tapped & refined to produce a granulated high-grade 30% FeNi product which
will be transported via truck to a bonded warehouse in the port of Vila do
Conde.

 

Figure 5 - Electric arc furnace

 

 

Figure 6 shows construction of the electrical sub-station, supplied by Vision.
Here, electricity from the 230kV transmission line will be received before
being distributed across the site. Low cost, renewable electricity will be
transmitted along the 126km powerline from the Xinguara Bay substation, the
only major offsite infrastructure required for the Araguaia project. To date,
240 out of 260 pylons have been erected and 42km of the conductor cables has
been installed.

 

Figure 6 - Electrical sub-station

 

 

3.      Commencement of ore stockpiling

As announced in early July, Araguaia's mining permit was approved ("Autoriza o
comissionamento da atividade de Extração Mineral") enabling the Company to
mine and stockpile ore in anticipation of commissioning, thereby optimising
the consistency of the feedstock. The first mineralised ore has since been
mined and stockpiling has begun. Over the course of the next six months,
further stockpiles will be established, with sufficient ore to feed the plant
for the subsequent six months. Fagundes, a leading Brazilian contract mining
services company began pre-stripping activities at the Pequizeiro pit in April
and to date have removed ~400kt of overburden.

 

Figure 7 - A view of the Pequizeiro pit

 

 

 

4.    Water storage reservoir

Construction of the water-storage reservoir has commenced. The next steps will
be elevation of the main embankment, internal drainage and jet grouting the
main embankment wall. The reservoir will provide a constant source of cooling
water to the process plant and act as a heat sink for the furnace. Over
Araguaia's life of mine, Horizonte expects ~ 90% of water used in the process
plant to be recycled.

 

Figure 8 - Water storage reservoir

 

 

5.      Environmental activities

With the onset of the dry season, management of dust from road traffic has
become an area of focus. In 2022 alone, Horizonte invested over BRL 50M in
state and municipal road upgrades - including widening, capping, safety
controls and bridge upgrades, making what were previously poor quality roads,
safe for increased levels of activity - benefiting the Company and local
communities. In relation to the management of dust, the Company continues
implementing its commitments in the sections of roads most impacted by Company
activities.  Beyond compliance, in the quarter this included the commencement
of sealing of roads adjacent to five small rural villages. As the roads are
state and municipal infrastructure, intended to be maintained through the
payment of taxes for the benefit of all road users, the additional BRL 2M
commitment to road sealing is a corporate social responsibility initiative of
the Company.

 

6.      Social activities

In the quarter, Horizonte continued to implement a range of social programmes
at Araguaia. In conformance with International Finance Corporation (IFC)
Performance Standard 5, the Company has been advancing various initiatives in
support of the families that are directly impacted by the project. The first
three houses for resettled families are now complete and agronomic support is
being provided as part of the livelihoods restoration and enhancement plan.
Also in the period, the Company continued the sampling of community water
supply systems and sharing the results of the water quality testing. None of
the results were project impacted, however valuable engagement occurred as the
Company raised awareness on 'safe' water supply, hygiene and health. The
programmes were well received by the community participants.

 

 

7.      Permitting

In the quarter and as previously announced, we were pleased to announce the
receipt of authorisation for the commencement of mining at Araguaia. In
Brazil, environmental licencing follows a three-stage process: i) preliminary
licence (LP), which is issued following assessment and acceptability of the
project proposal and impact assessment; ii) installation licence (LI) allowing
construction and other preliminary development, such as pre-stripping; and
iii) operational licence, allowing the use and operation of the
constructed/developed infrastructure. With the issuance of the mining
authorisation, Horizonte has commenced extraction and stockpiling of ore in
preparation of commissioning.

 

ARAGUAIA LINE 2: FEASIBILITY STUDY EXPECTED IN 2H 2023

 

In March 2023, Horizonte awarded the Araguaia Line 2 FS contracts aiming to
double nickel production to 29,000 tpa at Araguaia through the construction of
a duplicate RKEF processing facility ("Line 2"). Good progress has been made
to date and the Company continues to target publication of the study results
later this year. Araguaia line 2 is expected to deliver greater operational
flexibility, lower capital intensity and increased operating margins. The aim
of the FS is to produce a NI 43-101 Feasibility Report supported by a AACEI
Class 2-quality cost estimate, and project execution plan.

 

 

PROJECT FINANCING ACTIVITIES

 

As of 30 June 2023, a total of US$329 million has been spent on the Araguaia
construction out of the budgeted capital requirement of US$537 million.

 

As of 30 June 2023, US$140 million has been drawn down from the senior secured
project finance debt facility of US$346 million (the "Senior Debt Facility").
As of 30 June 2023, the Company had total liquidity sources of US$344 million
comprised of US$206 million undrawn on the Senior Debt Facility, a cash
position of US$108 million, and US$30 million on the Cost Overrun Facility
(which remains undrawn to date). After quarter-end, the Company successfully
passed its cost-to-complete test, in accordance with its lending terms, which
assessed the Company's funding headroom to carry-out the Araguaia Phase 1
project build to nameplate production, enabling the draw down of an additional
US$75m.

 

 

For further information, visit www.horizonteminerals.com
(http://www.horizonteminerals.com) or contact:

 

 Horizonte Minerals plc                                                     info@horizonteminerals.com (mailto:info@horizonteminerals.com)

 Jeremy Martin (CEO)                                                        +44 (0) 203 356 2901

 Simon Retter (CFO)

 Patrick Chambers (Head of IR)

 Peel Hunt LLP (Nominated Adviser & Joint Broker)                           +44 (0)20 7418 8900

 Ross Allister

 David McKeown

 BMO (Joint Broker)                                                         +44 (0) 20 7236 1010

 Thomas Rider

 Pascal Lussier Duquette

 Andrew Cameron

 Barclays (Joint Broker)                                                    +44 (0)20 7623 2323

 Philip Lindop

 Richard Bassingthwaighte

 Tavistock (Financial PR)                                                   +44 (0) 20 7920 3150

 Emily Moss

 Cath Drummond

 

 

ABOUT HORIZONTE MINERALS

Horizonte Minerals Plc (AIM/TSX: HZM) is developing two 100%-owned, Tier 1
projects in Pará state, Brazil - the Araguaia Nickel Project and the Vermelho
Nickel-Cobalt Project. Both projects are high-grade, low-cost, with low carbon
emission intensities and are scalable. Araguaia is under construction with
first metal scheduled for 1Q 2024. When fully ramped up with Line 1 and Line
2, Araguaia is forecast to produce 29,000 tonnes of nickel per year. Vermelho
is at feasibility study stage and is expected to supply nickel to the critical
metals market. Horizonte's combined production profile of over 60,000 tonnes
of nickel per year positions the Company as a globally significant nickel
producer. Horizonte's top three shareholders are La Mancha Investments S.à
r.l., Glencore Plc and Orion Resource Partners LLP.

 

CAUTIONARY STATEMENT REGARDING FORWARD-LOOKING INFORMATION

Except for statements of historical fact relating to the Company, certain
information contained in this press release constitutes "forward-looking
information" under Canadian securities legislation. Forward-looking
information includes, but is not limited to, the ability of the Company to
complete any planned acquisition of equipment, statements with respect to the
potential of the Company's current or future property mineral projects; the
ability of the Company to complete a positive feasibility study regarding the
second RKEF line at Araguaia on time, or at all, the ability of the Company to
complete a positive feasibility study regarding the Vermelho Project on time,
or at all, the success of exploration and mining activities; cost and timing
of future exploration, production and development; the costs and timing for
delivery of the equipment to be purchased, the estimation of mineral resources
and reserves and the ability of the Company to achieve its goals in respect of
growing its mineral resources; the realization of mineral resource and reserve
estimates and achieving production in accordance with the Company's potential
production profile or at all. Generally, forward-looking information can be
identified by the use of forward-looking terminology such as "plans",
"expects" or "does not expect", "is expected", "budget", "scheduled",
"estimates", "forecasts", "intends", "anticipates" or "does not anticipate",
or "believes", or variations of such words and phrases or statements that
certain actions, events or results "may", "could", "would", "might" or "will
be taken", "occur" or "be achieved". Forward-looking information is based on
the reasonable assumptions, estimates, analysis and opinions of management
made in light of its experience and its perception of trends, current
conditions and expected developments, as well as other factors that management
believes to be relevant and reasonable in the circumstances at the date that
such statements are made, and are inherently subject to known and unknown
risks, uncertainties and other factors that may cause the actual results,
level of activity, performance or achievements of the Company to be materially
different from those expressed or implied by such forward-looking information,
including but not limited to risks related to: the inability of the Company to
complete any planned acquisition of equipment on time or at all, the ability
of the Company to complete a positive feasibility study regarding the
implementation of a second RKEF line at Araguaia on the timeline contemplated
or at all, the ability of the Company to complete a positive feasibility study
regarding the Vermelho Project on the timeline contemplated or at all,
exploration and mining risks, competition from competitors with greater
capital; the Company's lack of experience with respect to development-stage
mining operations; fluctuations in metal prices; uninsured risks;
environmental and other regulatory requirements; exploration, mining and other
licences; the Company's future payment obligations; potential disputes with
respect to the Company's title to, and the area of, its mining concessions;
the Company's dependence on its ability to obtain sufficient financing in the
future; the Company's dependence on its relationships with third parties; the
Company's joint ventures; the potential of currency fluctuations and political
or economic instability in countries in which the Company operates; currency
exchange fluctuations; the Company's ability to manage its growth effectively;
the trading market for the ordinary shares of the Company; uncertainty with
respect to the Company's plans to continue to develop its operations and new
projects; the Company's dependence on key personnel; possible conflicts of
interest of directors and officers of the Company, and various risks
associated with the legal and regulatory framework within which the Company
operates, together with the risks identified and disclosed in the Company's
disclosure record available on the Company's profile on SEDAR at
www.sedar.com, including without limitation, the annual information form of
the Company for the year ended December 31, 2022, and the Araguaia and
Vermelho Technical Reports available on the Company's website
https://horizonteminerals.com/. Although management of the Company has
attempted to identify important factors that could cause actual results to
differ materially from those contained in forward-looking information, there
may be other factors that cause results not to be as anticipated, estimated or
intended. There can be no assurance that such statements will prove to be
accurate, as actual results and future events could differ materially from
those anticipated in such statements.

 

 1  (#_ftnref1) Calculated per million hours worked

This information is provided by RNS, the news service of the London Stock Exchange. RNS is approved by the Financial Conduct Authority to act as a Primary Information Provider in the United Kingdom. Terms and conditions relating to the use and distribution of this information may apply. For further information, please contact
rns@lseg.com (mailto:rns@lseg.com)
 or visit
www.rns.com (http://www.rns.com/)
.

RNS may use your IP address to confirm compliance with the terms and conditions, to analyse how you engage with the information contained in this communication, and to share such analysis on an anonymised basis with others as part of our commercial services. For further information about how RNS and the London Stock Exchange use the personal data you provide us, please see our
Privacy Policy (https://www.lseg.com/privacy-and-cookie-policy)
.   END  MSCFIFEETLIVIIV

Recent news on Horizonte Minerals

See all news