Picture of Iberdrola SA logo

IBE Iberdrola SA News Story

0.000.00%
es flag iconLast trade - 00:00
UtilitiesConservativeLarge CapHigh Flyer

GE Vernova must continue work on Vineyard Wind's wind farm, judge rules

BOSTON, April 17 (Reuters) - A Massachusetts judge on Friday blocked GE Vernova GEV.N from abandoning work on the largest offshore wind farm in New England after developer Vineyard Wind refused to pay over $300 million the turbine supplier says it is owed for the $4.5 billion project.

Suffolk County Superior Court Judge Peter Krupp in Boston issued a preliminary injunction at developer Vineyard Wind's request preventing a GE Vernova unit from terminating their contract and ceasing work effective April 28.

 (Reporting by Nate Raymond in Boston, Editing by Franklin Paul)

 ((Nate.Raymond@thomsonreuters.com; 347-243-6917; Reuters Messaging: nate.raymond.thomsonreuters.com@reuters.net))

Recent news on Iberdrola SA

See all news